Construction Update Three-Week Look Ahead April 22, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of April 18:

  • Install permanent traffic control at Stations 1, 21
  • Install daily traffic control at Stations 8, 19, 20, 32, 33
  • Construct restroom, grade, and form platform at Station 1
  • Survey Staking at Stations 1, 2
  • Install conduit at Stations 1, 28, 33
  • Install erosion control at Station 2
  • WE Energies boring at Station 8
  • Install glass and railings at Stations 19, 20
  • Sewer work at Station 21
  • Survey platform at Stations 28, 33
  • Common excavation and subgrade & install base course at Station 32
  • Stump grinding at Station 33

Week of April 25:

  • Install permanent traffic control at Stations 1, 2, 21
  • Install daily traffic control at Stations 8, 13, 16, 32, 33
  • Northbound and Southbound inside lane closure at Station 13
  • Construct restroom, survey staking, install snowmelt cable, pour platform, & form, pour, and cure curb and gutter at Station 1
  • Sawcutting at Stations 2, 16, 32, 33
  • Survey staking, remove concrete pavement, common excavation and subgrade, install base course, install platform conduit at Station 2
  • WE Energies boring at Station 8
  • Restoration at Stations 8, 11, 12, 13, 15, 17
  • Sawcut median crossover, median removal, and median stone at Station 13
  • Install sidewalk at Station 17
  • Sewer work at Station 21
  • Survey platform at Stations 21, 32
  • Install conduit at Stations 21, 33
  • Install snowmelt cable at Station 33

Week of May 2:

  • Install permanent traffic control at Stations 1, 2, 21
  • Install daily traffic control at Stations 32, 33
  • Northbound and Southbound inside lane closure and pave median at Station 13
  • Construct restroom, install pavement, install sidewalk at Station 1
  • Survey staking, install platform conduit, grade, form platform, and install snowmelt at Station 2
  • Install conduit at Station 21

East-West Bus Rapid Transit Construction Updates will be updated weekly.