Construction Update Three-Week Look Ahead April 29, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of April 25:

  • Install permanent traffic control at Stations 1, 13, 21
  • Install daily traffic control at Stations 8, 17, 32, 33
  • Construct restroom, form platform, install snowmelt cable, and pour platform at Station 1
  • Survey staking at Station 2
  • WE Energies boring at Station 8
  • Restoration at Stations 8, 11, 12, 13, 15, 17
  • Northbound and Southbound inside lane closure and sawcut median crossover at Station 13
  • Sewer work, boring street lights, and platform survey at Station 21
  • Sawcut Stations 32, 33
  • Steel encasement at Station 32
  • Stump grinding at Station 33

Week of May 2:

  • Install permanent traffic control at Stations 1, 2, 13, 21
  • Install daily traffic control at Stations 16, 32, 33
  • Construct restroom, survey staking, pour platform, install pavement & form, pour, and cure curb and gutter at Station 1
  • Sawcut, survey staking, remove concrete pavement, install base course, common excavation and subgrade Station 2
  • Northbound and Southbound inside lane closure, median removals, and install median stone at Station 13
  • Install conduit at Stations 21, 28, 33
  • Survey platform at Stations 28, 32, 33
  • Street Light Termination at Station 28
  • Install street light conduit at Station 32
  • City Street Lighting Relocate at Station 33

Week of May 9:

  • Install permanent traffic control at Stations 1, 2, 13
  • Install daily traffic control at Stations 16, 32, 33
  • Construct restroom, install pavement, and install sidewalk at Station 1
  • Survey Staking, install platform conduit, form platform and grade Station 2
  • Northbound and Southbound inside lane closure, pave median, install temp pavement markings, remove concrete pavement, common excavation and subgrade at Station 13
  • Grade Stations 28, 32
  • Form platform at Stations 28, 32, 33
  • Install conduit at Station 28
  • Install platform conduit at Station 32
  • Install snowmelt cable at Station 33

East-West Bus Rapid Transit Construction Updates will be updated weekly.