East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.
Week of April 4:
- Install permanent traffic control at Stations 1, 21
- Install daily traffic control at Stations 11, 12, 13, 14, 15, 17, 18, 19, 20, 28, 33
- Construct restroom and survey staking at Station 1
- Grade Stations 1, 20
- WE Energies boring at Station 8
- Form, pour, and cure curb and gutter and install 12” pavement at Stations 11, 12, 13
- Install sidewalk at Stations 11, 12, 13, 20
- Install shelter at Stations 11, 12, 14, 17, 18, 19
- Install glass and railings at Stations 18, 19
- Stake curb ramps at Station 20
- Sewer work, survey platform, and install conduit at Station 21
- Install base course at Stations 21, 28
- Install inlet protection, remove concrete pavement, and common excavation and subgrade Station 28
- Sawcutting at Stations 28, 33
Week of April 11:
- Install permanent traffic control at Stations 1, 21
- Install daily traffic control at Stations 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17, 20
- Construct restroom and install snowmelt cable at Station 1
- Form platform at Stations 1, 21, 28
- Install conduit at Stations 1, 21, 28, 33
- Install glass and railings at Stations 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14
- Form, pour, and cure curb and gutter and install 12” pavement at Stations 15, 17
- Install sidewalk at Stations 15, 17, 20
- Install median nose at Station 15
- Install shelter at Stations 15, 20
- Survey platform at Stations 21, 28, 33
- Station snowmelt install at Station 21
- Common excavation and subgrade, remove concrete pavement, and install base course at Station 33
Week of April 18:
- Install permanent traffic control at Stations 1, 21
- Construct restroom, survey staking, pour platform, and form, pour, and cure curb and gutter at Station 1
- Install snowmelt cable at Stations 1, 33
- Install daily traffic control at Stations 11, 12, 15, 17, 20, 30, 31, 32
- Install glass and railings at Stations 15, 17, 20
- Station snowmelt install at Station 21
- Sawcutting at Stations 30, 31, 32
- Install conduit and form platform at Station 33
East-West Bus Rapid Transit Construction Updates will be updated weekly.