Construction Update Three-Week Look Ahead April 8, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of April 4:

  • Install permanent traffic control at Stations 1, 21
  • Install daily traffic control at Stations 11, 12, 13, 14, 15, 17, 18, 19, 20, 28, 33
  • Construct restroom and survey staking at Station 1
  • Grade Stations 1, 20
  • WE Energies boring at Station 8
  • Form, pour, and cure curb and gutter and install 12” pavement at Stations 11, 12, 13
  • Install sidewalk at Stations 11, 12, 13, 20
  • Install shelter at Stations 11, 12, 14, 17, 18, 19
  • Install glass and railings at Stations 18, 19
  • Stake curb ramps at Station 20
  • Sewer work, survey platform, and install conduit at Station 21
  • Install base course at Stations 21, 28
  • Install inlet protection, remove concrete pavement, and common excavation and subgrade Station 28
  • Sawcutting at Stations 28, 33

Week of April 11:

  • Install permanent traffic control at Stations 1, 21
  • Install daily traffic control at Stations 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17, 20
  • Construct restroom and install snowmelt cable at Station 1
  • Form platform at Stations 1, 21, 28
  • Install conduit at Stations 1, 21, 28, 33
  • Install glass and railings at Stations 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14
  • Form, pour, and cure curb and gutter and install 12” pavement at Stations 15, 17
  • Install sidewalk at Stations 15, 17, 20
  • Install median nose at Station 15
  • Install shelter at Stations 15, 20
  • Survey platform at Stations 21, 28, 33
  • Station snowmelt install at Station 21
  • Common excavation and subgrade, remove concrete pavement, and install base course at Station 33

Week of April 18:

  • Install permanent traffic control at Stations 1, 21
  • Construct restroom, survey staking, pour platform, and form, pour, and cure curb and gutter at Station 1
  • Install snowmelt cable at Stations 1, 33
  • Install daily traffic control at Stations 11, 12, 15, 17, 20, 30, 31, 32
  • Install glass and railings at Stations 15, 17, 20
  • Station snowmelt install at Station 21
  • Sawcutting at Stations 30, 31, 32
  • Install conduit and form platform at Station 33

East-West Bus Rapid Transit Construction Updates will be updated weekly.

construction-map-with-stations