Construction Update Three-Week Look Ahead August 5, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of August 1:

  • Install permanent traffic control at Stations 1, 13, 21, 24, 26
  • Install daily traffic control at Stations 2, 16, 23, 25, 30
  • Set shelter at Station 2
  • Pour sidewalk and platform ramps at Station 13
  • Install platform conduit and grade at Station 16
  • Install shelter and restore at Station 21
  • Survey staking at Stations 23, 26
  • Remove street lights at Station 23
  • Install platform conduit at Stations 23, 25
  • Pour 12” pavement at Station 24
  • Install base course and form platform at Station 25
  • Install snowmelt at Stations 25, 26
  • Pour platform at Station 26
  • Common excavation and subgrade & remove concrete at Station 30
  • Pour concrete leveling pad at Station 32

Week of August 8:

  • Install permanent traffic control at Stations 1, 13, 24, 26
  • Install daily traffic control at Stations 16, 23, 25, 30
  • Pour sidewalk at Stations 13, 25, 26
  • Install platform conduit at Stations 16, 23
  • Install glass at Station 21
  • Remove concrete at Stations 23, 30
  • Pour 12” pavement at Stations 24, 26
  • Survey staking at Stations 25, 30
  • Install snowmelt and pour platform at Station 25
  • Form and pour curb and gutter at Stations 25, 26
  • Install trench drain, install platform ramp snowmelt & form and pour ramps at Station 26
  • Common excavation and subgrade, install base course, and remove street lights at Station 30

Week of August 15:

  • Install permanent traffic control at Stations 1, 13, 24, 26
  • Install daily traffic control at Stations 16, 23, 25, 30, 31
  • Form platform and install snowmelt cable at Stations 16, 23
  • Survey staking at Station 23
  • Form and pour curb and gutter at Station 25
  • Pour 12” pavement and sidewalk at Station 26
  • Install platform conduit at Station 30
  • Remove concrete, common excavation and subgrade, install base course & remove street lights at Station 31

East-West Bus Rapid Transit Construction Updates will be updated weekly.

Construction Map with Stations July 9, 2021