East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.
Week of August 1:
- Install permanent traffic control at Stations 1, 13, 21, 24, 26
- Install daily traffic control at Stations 2, 16, 23, 25, 30
- Set shelter at Station 2
- Pour sidewalk and platform ramps at Station 13
- Install platform conduit and grade at Station 16
- Install shelter and restore at Station 21
- Survey staking at Stations 23, 26
- Remove street lights at Station 23
- Install platform conduit at Stations 23, 25
- Pour 12” pavement at Station 24
- Install base course and form platform at Station 25
- Install snowmelt at Stations 25, 26
- Pour platform at Station 26
- Common excavation and subgrade & remove concrete at Station 30
- Pour concrete leveling pad at Station 32
Week of August 8:
- Install permanent traffic control at Stations 1, 13, 24, 26
- Install daily traffic control at Stations 16, 23, 25, 30
- Pour sidewalk at Stations 13, 25, 26
- Install platform conduit at Stations 16, 23
- Install glass at Station 21
- Remove concrete at Stations 23, 30
- Pour 12” pavement at Stations 24, 26
- Survey staking at Stations 25, 30
- Install snowmelt and pour platform at Station 25
- Form and pour curb and gutter at Stations 25, 26
- Install trench drain, install platform ramp snowmelt & form and pour ramps at Station 26
- Common excavation and subgrade, install base course, and remove street lights at Station 30
Week of August 15:
- Install permanent traffic control at Stations 1, 13, 24, 26
- Install daily traffic control at Stations 16, 23, 25, 30, 31
- Form platform and install snowmelt cable at Stations 16, 23
- Survey staking at Station 23
- Form and pour curb and gutter at Station 25
- Pour 12” pavement and sidewalk at Station 26
- Install platform conduit at Station 30
- Remove concrete, common excavation and subgrade, install base course & remove street lights at Station 31
East-West Bus Rapid Transit Construction Updates will be updated weekly.