Construction Update Three-Week Look Ahead August 6, 2021

Construction Update

We want to keep you informed

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below: 

Week of August 2:

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9
  • Form platform at Stations 3, 4
  • Install snowmelt, pull boxes, and grounding ring at Station 3
  • Regrade Stations 3, 4, 5, 6, 7, 8
  • Survey platform at Stations 7, 8
  • Install conduit at Station 7
  • Street lighting relocation at Station 8
  • Remove concrete pavement at Station 9
  • Common excavation at Station 9

Week of August 9: 

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10
  • Install snowmelt, pull boxes, and grounding ring at Stations 3, 4
  • Form and pour curb and gutter at Station 3
  • Pour platform at Station 3
  • Form platform at Station 4
  • Install conduit at Stations 7, 8
  • Install base course at Stations 9, 10
  • Remove concrete pavement at Station 10
  • Common excavation at Station 9, 10

Week of August 16: 

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11
  • Install sidewalk at Station 3
  • Install 12” pavement at Station 3
  • Form and pour curb and gutter at Station 4
  • Install snowmelt, pull boxes and grounding ring at Station 5
  • Pour platform at Station 4
  • Form platform at Station 5
  • Install conduit at Stations 9, 10
  • Remove concrete pavement at Station 11
  • Common excavation at Station 11
  • Install base course at Station 11

East-West Bus Rapid Transit Construction Updates will be updated weekly. 

construction-map-with-stations