Week of Dec. 13:

  • Install permanent traffic control at Stations 1, 20
  • Install daily traffic control at Stations 6, 18, 19
  • Restroom construction at Station 1
  • Re-install signs at Station 6
  • Backfill and restore Stations 18, 19
  • Install snowmelt, pull boxes, and grounding ring, adjust manhole, inspect snowmelt, pour platform, survey, install ramp and steps, install 12” pavement, & form, pour, and cure curb and gutter at Station 20

Week of Dec. 20:

  • Install permanent traffic control and restroom construction at Station 1
  • Install permanent traffic control, snowmelt inspection, install ramp and steps, install sidewalk, install 12” pavement, & form, pour, and cure curb and gutter at Station 20

Week of Dec. 27:

  • Install permanent traffic control and restroom construction at Station 1

East-West Bus Rapid Transit Construction Updates will be updated weekly. 