East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.
Week of Dec. 20:
- Install permanent traffic control at Stations 1, 20
- Restroom construction at Station 1
- Install snowmelt, pull boxes, grounding ring, sidewalk, and 12” pavement & snowmelt inspection, form, pour, and cure curb and gutter at Station 20
Week of Dec. 27:
- Install permanent traffic control at Stations 1, 20
- Restroom construction at Station 1
- Install ramp and steps, sidewalk, and 12” pavement at Station 20
Week of Jan. 3:
- Install permanent traffic control at Station 1
- Restroom construction at Station 1
East-West Bus Rapid Transit Construction Updates will be updated weekly.