Construction Update Three-Week Look Ahead December 3, 2021

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.

Week of Nov. 29:

  • Install permanent traffic control at Stations 1, 14, 15, 18, 19, 20
  • Install daily traffic control at Station 17
  • Install signal base at Stations 14, 15, 17
  • Install sidewalk at Stations 14, 17, 19
  • Form, pour, and cure curb and gutter at Station 15
  • Install snowmelt, pull boxes, and grounding ring, snowmelt inspection, & remove pavement and pothole at Station 18
  • Install ramp and steps at Stations 18, 19
  • Install conduit at Stations 19, 20
  • Terminate street lights at Station 20

Week of Dec. 6:

  • Install permanent traffic control at Stations 1, 14, 15, 18, 19, 20
  • Install daily traffic control at Station 17
  • Install sidewalk at Stations 14, 17, 18, 19
  • Form, pour, and cure curb and gutter at Station 15
  • Install 12” pavement at Station 18
  • Install conduit, regrade, adjust manhole, & form platform at Station 20

Week of Dec. 13:

  • Install permanent traffic control at Stations 1, 20
  • Restroom construction at Station 1
  • Install snowmelt, pull boxes, and grounding ring, snowmelt inspection, pour platform, grade, survey, & install ramp and steps at Station 20

East-West Bus Rapid Transit Construction Updates will be updated weekly. 