Construction Update Three-Week Look Ahead December 31, 2021

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of Dec. 27:

  • Install permanent traffic control at Stations 1, 20
  • Construct restroom at Station 1
  • Install ramp and steps, temporary sidewalk, and 12” pavement at Station 20

Week of Jan. 3:

  • Install permanent traffic control and restroom construction at Station 1

Week of Jan. 10:

  • Install permanent traffic control and construct restroom at Station 1
  • Install daily traffic control and shelters at Stations 3, 4, 6, 7, 8, 9, 10

East-West Bus Rapid Transit Construction Updates will be updated weekly. 