East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.
Week of Feb. 7:
- Install permanent traffic control at Stations 1
- Construct restroom at Station 1
Week of Feb. 14:
- Install permanent traffic control at Station 1
- Construct restroom at Station 1
Week of Feb. 21:
- Install permanent traffic control at Station 1
- Construct restroom at Station 1
East-West Bus Rapid Transit Construction Updates will be updated weekly.