Week of June 27:

  • Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24, 26
  • Install daily traffic control at Stations 16, 28, 32, 33
  • Full lane closure at Station 16
  • Construct restroom at Station 1
  • Install shelter at Stations 1, 28, 32, 33
  • Pour sidewalk at Stations 2, 28
  • Install platform conduit & Northbound and Southbound lane closures at Station 13
  • Survey Staking at Stations 13, 24
  • Install base course at Stations 13, 26
  • Sewer work, survey, and grade at Station 16
  • Form, pour, cure curb and gutter, form platform ramps, and install platform ramp snowmelt at Station 21
  • Install snowmelt at Station 24

Week of July 4:

  • Install permanent traffic control at Stations 1, 13, 21, 22, 24, 26
  • Install daily traffic control at Stations 16, 28, 32, 33
  • Construct restroom at Station 1
  • Form platform, install snowmelt cable, & Northbound and Southbound lane closures at Station 13
  • Survey Station 16
  • Grade Stations 16, 24
  • Pour and cure pavement & pour platform ramps at Station 21
  • Pour platform at Station 24
  • Install platform conduit, survey staking, sewer work, and street light removals at Station 26

Week of July 11:

  • Install permanent traffic control at Stations 1, 13, 21, 22, 24, 26
  • Install daily traffic control at Stations 2, 16
  • Construct restroom at Station 1
  • Pour platform ramps at Station 2
  • Install trench drain, form platform, & Northbound and Southbound lane closures at Station 13
  • Pour sidewalk at Station 21
  • Form, pour, cure curb and gutter, install platform ramp snowmelt, and pour ramps at Station 24
  • Install platform ramp conduit, grade, and form platform at Station 26

 