East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.
Week of July 11:
- Install permanent traffic control at Stations 1, 13, 21, 22, 24, 26
- Install daily traffic control at Stations 16, 25, 28, 32
- Construct restroom at Station 1
- Northbound and Southbound lane closures, install snowmelt cable, and form platform at Station 13
- Survey staking and install trench drain at Stations 13, 24
- Survey and install platform conduit at Station 16
- Grade Stations 16, 24
- Pour platform ramps at Station 21
- Pour sidewalk at Stations 21, 24, 28
- Pour platform, form, pour, and cure curb & gutter, install platform ramp snowmelt, and form ramps at Station 24
- Install erosion control at Stations 25, 30, 31
- Sawcutting at Station 25
- Sewer work at Station 26
- Pour concrete leveling pad at Station 32
Week of July 18:
- Install permanent traffic control at Stations 1, 13, 22, 24, 26
- Install daily traffic control at Stations 16, 25, 30, 31
- Construct restroom and restore Station 1
- Northbound and Southbound lane closures, grade, form, pour, and cure curb & gutter, pour driveways, form platform ramps, and install platform ramp snowmelt at Station 13
- Survey staking at Stations 13, 25, 26
- Install platform conduit at Stations 16, 26
- Form platform and install snowmelt cable at Station 16
- Pour 12” pavement and pour sidewalk at Station 24
- Remove concrete & common excavation and subgrade at Stations 25, 30, 31
- Install base course at Stations 25, 30
- Street Light removals at Station 26
- Sawcutting at Stations 30, 31
Week of July 25:
- Install permanent traffic control at Stations 1, 13, 21, 22, 24, 26
- Install daily traffic control at Stations 2, 16, 25, 30, 31
- Construct restroom at Station 1
- Set shelter at Stations 2, 24
- Restoration at Station 2
- Northbound and Southbound lane closures & pour and cure pavement at Station 13
- Grade and install snowmelt cable at Station 16
- Pour platform at Stations 16, 26
- Install shelter and glass at Station 21
- Install platform conduit at Stations 25, 30, 31
- Form platform at Stations 25, 26
- Install snowmelt at Station 26
- Street Light removals at Stations 30, 31
- Common excavation and subgrade & install base course at Station 31
East-West Bus Rapid Transit Construction Updates will be updated weekly.