Construction Update Three-Week Look Ahead July 15, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of July 11:

  • Install permanent traffic control at Stations 1, 13, 21, 22, 24, 26
  • Install daily traffic control at Stations 16, 25, 28, 32
  • Construct restroom at Station 1
  • Northbound and Southbound lane closures, install snowmelt cable, and form platform at Station 13
  • Survey staking and install trench drain at Stations 13, 24
  • Survey and install platform conduit at Station 16
  • Grade Stations 16, 24
  • Pour platform ramps at Station 21
  • Pour sidewalk at Stations 21, 24, 28
  • Pour platform, form, pour, and cure curb & gutter, install platform ramp snowmelt, and form ramps at Station 24
  • Install erosion control at Stations 25, 30, 31
  • Sawcutting at Station 25
  • Sewer work at Station 26
  • Pour concrete leveling pad at Station 32

Week of July 18:

  • Install permanent traffic control at Stations 1, 13, 22, 24, 26
  • Install daily traffic control at Stations 16, 25, 30, 31
  • Construct restroom and restore Station 1
  • Northbound and Southbound lane closures, grade, form, pour, and cure curb & gutter, pour driveways, form platform ramps, and install platform ramp snowmelt at Station 13
  • Survey staking at Stations 13, 25, 26
  • Install platform conduit at Stations 16, 26
  • Form platform and install snowmelt cable at Station 16
  • Pour 12” pavement and pour sidewalk at Station 24
  • Remove concrete & common excavation and subgrade at Stations 25, 30, 31
  • Install base course at Stations 25, 30
  • Street Light removals at Station 26
  • Sawcutting at Stations 30, 31

Week of July 25:

  • Install permanent traffic control at Stations 1, 13, 21, 22, 24, 26
  • Install daily traffic control at Stations 2, 16, 25, 30, 31
  • Construct restroom at Station 1
  • Set shelter at Stations 2, 24
  • Restoration at Station 2
  • Northbound and Southbound lane closures & pour and cure pavement at Station 13
  • Grade and install snowmelt cable at Station 16
  • Pour platform at Stations 16, 26
  • Install shelter and glass at Station 21
  • Install platform conduit at Stations 25, 30, 31
  • Form platform at Stations 25, 26
  • Install snowmelt at Station 26
  • Street Light removals at Stations 30, 31
  • Common excavation and subgrade & install base course at Station 31

East-West Bus Rapid Transit Construction Updates will be updated weekly.