Construction Update Three-Week Look Ahead July 16, 2021

Construction Update

We want to keep you informed

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below: 

Week of July 12:

  • Install Permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8
  • Install Daily traffic control at Stations 10, 14, 15, 16, 17 
  • Install Restroom concrete at Station 1
  • Install Rough-In plumbing (Restroom) at Station 1
  • Pour Restroom Floor at Station 1
  • Form Platform at Station 3
  • Install and inspect Conduits at Station 5
  • Gas Valve Adjustment at Station 8
  • Install Temporary Street Light at Station 10  
  • Install Directional Bore 3” Conduit at Stations 14, 15, 16, 17

Week of July 19:

  • Install Permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8
  • Install Daily traffic control at Stations 16, 17
  • Install Snowmelt, Pull Boxes, and Grounding Ring at Stations 3, 4
  • Pour Platform at Station 3
  • Form Platform at Stations 4, 6
  • Manhole Adjustment at Station 5
  • Install sewer at Station 7
  • Install conduit at Station 7
  • Install Directional Bore 3” Conduit at Stations 16, 17

Week of July 26:

  • Install Permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8
  • Install Snowmelt, Pull boxes, and Grounding Ring at Stations 4, 6
  • Pour platform at Stations 3, 4
  • Form/Pour/Cure Curb and Gutter at Station 3
  • Install Sidewalk at Station 3
  • Form platform at Station 6
  • Install Conduits at Station 7, 8
  • Install Sewer and adjust water at Station 8
  • Install Survey Platform at Station 8

East-West Bus Rapid Transit Construction Updates will be updated weekly. 