Construction Update Three-Week Look Ahead July 22, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of July 18:

  • Install permanent traffic control at Stations 1, 13, 21, 24, 26
  • Install daily traffic control at Stations 2, 16, 23, 25, 30, 31
  • Construct restroom at Station 1
  • Restore Stations 1, 2, 21
  • Survey staking at Stations 13, 23, 25, 26
  • Northbound and Southbound lane closures, form, pour, and cure curb & gutter, pour driveways, grade, and form platform ramps at Station 13
  • Install trench drain and platform ramp snowmelt at Stations 13, 24
  • Survey Station 16
  • Install erosion control at Station 23
  • Form ramps and pour sidewalk at Station 24
  • Common excavation & subgrade, remove concrete, and install base course at Station 25
  • Install platform conduit at Station 26
  • Sawcut Stations 30, 31

Week of July 25:

  • Install permanent traffic control at Stations 1, 13, 21, 24, 26
  • Install daily traffic control at Stations 2, 16, 23, 25, 30, 31
  • Construct restroom at Station 1
  • Set shelter at Station 2
  • Northbound and Southbound lane closures, pour and cure pavement, pour driveways and platform ramps, & pour sidewalk at Station 13
  • Install platform conduit at Stations 16, 25
  • Install shelter and glass at Station 21
  • Survey staking at Station 23
  • Common excavation & subgrade and remove concrete at Stations 23, 30
  • City street lighting conduit termination and install base course at Station 23
  • Relocate street lights at Station 25
  • Sewer work, form platform, and install snowmelt at Station 26

Week of August 1:

  • Install permanent traffic control at Stations 1, 13, 24, 26
  • Install daily traffic control at Stations 16, 23, 25, 30, 31
  • Pour sidewalk at Station 13
  • Grade and install snowmelt cables at Station 16
  • Form platform at Stations 16, 25
  • Remove street lights at Stations 23, 30, 31
  • Install platform conduit at Stations 23, 25, 30
  • Pour 12” pavement at Station 24
  • Install base course at Stations 25, 30, 31
  • Install snowmelt at Stations 25, 26
  • Survey Staking and pour platform at Station 26
  • Common excavation and subgrade at Stations 30, 31
  • Remove concrete at Station 31

East-West Bus Rapid Transit Construction Updates will be updated weekly.

construction-map-with-stations