Construction Update Three-Week Look Ahead July 29, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of July 25:

  • Install permanent traffic control at Stations 1, 13, 24, 26
  • Install daily traffic control at Stations 16, 23, 25
  • Northbound and Southbound lane closures, grade, pour and cure pavement, form platform ramps, & install platform ramp snowmelt at Station 13
  • Install platform conduit at Stations 16, 25
  • Survey staking, remove concrete, common excavation and subgrade, install base course, & City Street Lighting conduit termination at Station 23
  • Relocate street light at Station 25
  • Sewer work and grading, form platform, & install snowmelt at Station 26

Week of August 1:

  • Install permanent traffic control at Stations 1, 13, 21, 24, 26
  • Install daily traffic control at Stations 2, 16, 23, 25, 30
  • Set shelter at Station 2
  • Pour platform ramps and sidewalk at Station 13
  • Install snowmelt cable and grading at Station 16
  • Install platform conduit at Stations 16, 23, 25
  • Form platform at Stations 16, 25
  • Install shelter and glass & restoration at Station 21
  • Street Light removals at Station 23
  • Install base course at Stations 25, 30
  • Install snowmelt at Stations 25, 26
  • Survey staking, pour platform, install trench drain, & form, pour, cure curb and gutter at Station 26
  • Common excavation and subgrade at Station 30

Week of August 8:

  • Install permanent traffic control at Stations 1, 13, 24, 26
  • Install daily traffic control at Stations 16, 23, 25, 30, 31
  • Survey Station 16
  • Install snowmelt cable at Stations 16, 23
  • Pour platform at Stations 16, 25
  • Form, pour, cure curb and gutter at Stations 16, 25, 26
  • Survey staking at Stations 23, 25
  • Remove concrete at Stations 23, 31
  • Install platform conduit at Stations 23, 30
  • Form platform at Station 23
  • Pour 12” pavement at Stations 24, 26
  • Install snowmelt at Station 25
  • Install platform ramp snowmelt, form and pour ramps, & pour sidewalk at Station 26
  • Common excavation and subgrade & remove street lights at Stations 30, 31
  • Install base course at Station 31

East-West Bus Rapid Transit Construction Updates will be updated weekly.

construction-map-with-stations