Construction Update Three-Week Look Ahead July 30, 2021

Construction Update

We want to keep you informed

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below: 

Week of July 26:

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8
  • Water line work at Station 8

Week of August 2:

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8
  • Form platform at Stations 3, 4
  • Install snowmelt, pull boxes, and grounding ring at Station 3
  • Regrade Stations 7, 8
  • Survey platform at Stations 7, 8
  • Install conduit at Station 7

Week of August 9:

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8
  • Pour platform at Stations 3, 4
  • Form/pour/cure curb and gutter at Station 3
  • Install sidewalk at Station 3
  • Install snowmelt, pull boxes, and grounding ring at Stations 4, 5
  • Form platform at Stations 4, 5, 6
  • Install conduit at Station 8

East-West Bus Rapid Transit Construction Updates will be updated weekly. 