East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below:
Week of July 5:
- Permanent traffic control installed at Stations 1, 3, 4, 5, 6, 7, 8
- Conduits installed at Stations 5, 6
- Survey Platform installed at Station 7
- Test Curbs poured at 1525 W. Vine St.
Week of July 12:
- Permanent traffic control installed at Stations 1, 3, 4, 5, 6, 7, 8<
- Daily traffic control installed at Stations 14, 15, 16, 17
- Restroom concrete installed at Station 1
- Rough-In plumbing (Restroom) installed at Stations 1
- Manhole adjustment at Station 5
- Sewers installed at Station 7
- Conduits installed at Stations 7, 8
- Sewers installed at Station 8
- Directional Bore 3” Conduit installed at Stations 14, 15
Week of July 19:
- Permanent traffic control installed at Stations 1, 3, 4, 5, 6, 7, 8
- Daily traffic control at Stations 16, 17
- Restroom floor poured at Station 1
- Snowmelt, Pull Boxes, and Grounding Ring installed at Stations 3, 4
- Platform poured at Station 3
- Form Platform at Stations 4, 6
- Conduits installed at Station 7
- Directional Bore 3” Conduit installed at Stations 16, 17
East-West Bus Rapid Transit Construction Updates will be updated weekly.