Construction Update Three-Week Look Ahead July 9, 2021

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below: 

Week of July 5:

  • Permanent traffic control installed at Stations 1, 3, 4, 5, 6, 7, 8
  • Conduits installed at Stations 5, 6
  • Survey Platform installed at Station 7
  • Test Curbs poured at 1525 W. Vine St. 

Week of July 12:

  • Permanent traffic control installed at Stations 1, 3, 4, 5, 6, 7, 8<
  • Daily traffic control installed at Stations 14, 15, 16, 17 
  • Restroom concrete installed at Station 1
  • Rough-In plumbing (Restroom) installed at Stations 1
  • Manhole adjustment at Station 5
  • Sewers installed at Station 7
  • Conduits installed at Stations 7, 8
  • Sewers installed at Station 8
  • Directional Bore 3” Conduit installed at Stations 14, 15 

Week of July 19:

  • Permanent traffic control installed at Stations 1, 3, 4, 5, 6, 7, 8
  • Daily traffic control at Stations 16, 17
  • Restroom floor poured at Station 1
  • Snowmelt, Pull Boxes, and Grounding Ring installed at Stations 3, 4
  •  Platform poured at Station 3
  • Form Platform at Stations 4, 6
  • Conduits installed at Station 7
  • Directional Bore 3” Conduit installed at Stations 16, 17

East-West Bus Rapid Transit Construction Updates will be updated weekly. 

Construction Map with Stations July 9, 2021