East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.
Week of June 6:
- Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24, 26, 28, 32
- Install daily traffic control at Stations 16, 33
- Construct restroom at Station 1
- Pour and cure pavement at Station 2
- Install platform conduit, Northbound & Southbound lane closures, and street light work at Station 13
- Install station snowmelt at Station 21
- Sawcutting at Stations 22, 26
- Remove concrete and install base course at Station 22
- Common excavation and subgrade Stations 22, 32
- City Street Lighting conduit termination at Stations 22, 24
- Survey staking and Street Light removals at Station 24
- Survey and pour platform at Station 28
Week of June 13:
- Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24, 26, 32
- Install daily traffic control at Stations 16, 28, 33
- Construct restroom at Station 1
- Form and pour platform ramps at Stations 2, 28, 33
- Install platform ramp snowmelt at Stations 2, 28
- Install platform conduit, Northbound & Southbound lane closures, and form platform at Station 13
- Survey staking at Stations 13, 22, 24, 26
- Survey and pour platform at Station 21
- Grade Stations 21, 24
- City Street Lighting conduit termination at Stations 22, 26
- Street Light Removals at Station 22
- Install platform conduit at Station 24
- Remove concrete, common excavation & subgrade, sewer work and install base course at Station 26
- Form, pour, and cure curb & gutter at Stations 28, 32
- Pour sidewalk at Station 28
- Install sidewalk at Station 33
Week of June 20:
- Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24, 26, 32
- Install daily traffic control at Stations 16, 28, 33
- Construct restroom at Station 1
- Pour sidewalk at Station 2
- Install snowmelt cable and Northbound & Southbound lane closures at Station 13
- Survey staking at Stations 13, 24, 26
- Form platform at Stations 13, 22, 24
- Sewer work at Station 16
- Install platform ramp snowmelt & form, pour, and cure curb, gutter, pavement, and platform ramps at Station 21
- Install platform conduit at Stations 22, 24
- Grade Station 22
- City Street Lighting conduit termination and Street Light Removals at Station 26
East-West Bus Rapid Transit Construction Updates will be updated weekly.