Construction Update Three-Week Look Ahead June 10, 2022

Construction Update
East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 
 
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 
 

Week of June 6:

  • Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24, 26, 28, 32
  • Install daily traffic control at Stations 16, 33
  • Construct restroom at Station 1
  • Pour and cure pavement at Station 2
  • Install platform conduit, Northbound & Southbound lane closures, and street light work at Station 13
  • Install station snowmelt at Station 21
  • Sawcutting at Stations 22, 26
  • Remove concrete and install base course at Station 22
  • Common excavation and subgrade Stations 22, 32
  • City Street Lighting conduit termination at Stations 22, 24
  • Survey staking and Street Light removals at Station 24
  • Survey and pour platform at Station 28

Week of June 13:

  • Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24, 26, 32
  • Install daily traffic control at Stations 16, 28, 33
  • Construct restroom at Station 1
  • Form and pour platform ramps at Stations 2, 28, 33
  • Install platform ramp snowmelt at Stations 2, 28
  • Install platform conduit, Northbound & Southbound lane closures, and form platform at Station 13
  • Survey staking at Stations 13, 22, 24, 26
  • Survey and pour platform at Station 21
  • Grade Stations 21, 24
  • City Street Lighting conduit termination at Stations 22, 26
  • Street Light Removals at Station 22
  • Install platform conduit at Station 24
  • Remove concrete, common excavation & subgrade, sewer work and install base course at Station 26
  • Form, pour, and cure curb & gutter at Stations 28, 32
  • Pour sidewalk at Station 28
  • Install sidewalk at Station 33

Week of June 20:

  • Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24, 26, 32
  • Install daily traffic control at Stations 16, 28, 33
  • Construct restroom at Station 1
  • Pour sidewalk at Station 2
  • Install snowmelt cable and Northbound & Southbound lane closures at Station 13
  • Survey staking at Stations 13, 24, 26
  • Form platform at Stations 13, 22, 24
  • Sewer work at Station 16
  • Install platform ramp snowmelt & form, pour, and cure curb, gutter, pavement, and platform ramps at Station 21
  • Install platform conduit at Stations 22, 24
  • Grade Station 22
  • City Street Lighting conduit termination and Street Light Removals at Station 26

East-West Bus Rapid Transit Construction Updates will be updated weekly.