East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.
Week of June 13:
- Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24, 26
- Install daily traffic control at Stations 16, 28, 32, 33
- Construct restroom at Station 1
- Install platform ramp snowmelt at Stations 2, 28
- Pour platform ramps at Station 2
- Install platform conduit, form platform & Northbound and Southbound lane closures at Station 13
- Survey Staking at Stations 13, 22, 24, 26
- Survey and pour platform at Station 21
- Street light removals and install base course at Station 22
- City Street Lighting conduit termination at Stations 22, 26
- Install platform conduit and street light removals at Station 24
- Concrete removals & common excavation and subgrade at Station 26
- Grade Station 28
- Install 12” pavement at Station 32
- Form and pour platform ramps at Station 33
Week of June 20:
- Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24, 26
- Install daily traffic control at Stations 16, 28, 32, 33
- Construct restroom and bollards at Station 1
- Pour sidewalk at Stations 2, 28
- Install snowmelt cable & Northbound and Southbound lane closures at Station 13
- Survey Staking at Stations 13, 24, 26
- Form platform at Stations 13, 24
- Sewer work at Stations 16, 26
- Grade Stations 21, 24
- Form, pour, and cure curb and gutter at Stations 21, 28
- Form platform ramps and install platform ramp snowmelt at Station 21
- Install platform conduit and pour platform at Station 24
- City Street Lighting conduit termination, install base course, and street light removals at Station 26
- Form and pour platform ramps at Station 28
- Install sidewalk at Station 33
Week of June 27:
- Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24, 26
- Install daily traffic control at Stations 16, 28, 32, 33
- Construct restroom at Station 1
- Install shelter at Stations 1, 2, 28, 32, 33
- Northbound and Southbound lane closures at Station 13
- Full lane closure and sewer work at Station 16
- Pour and cure pavement & pour platform ramps at Station 21
- Pour 12” pavement, platform ramp snowmelt, form ramps, form, pour, and cure curb & gutter, pour platform, and survey staking at Station 24
- Street Light removals and install platform conduit at Station 26
East-West Bus Rapid Transit Construction Updates will be updated weekly.