East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.
Week of June 20:
- Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24, 26
- Install daily traffic control at Stations 16, 28, 32, 33
- Construct restroom and install bollards at Station 1
- Pour platform ramps and sidewalk at Stations 2, 28
- Northbound and Southbound lane closures at Station 13
- Survey Staking at Stations 13, 24, 26
- Install platform conduit at Stations 13, 24
- Sewer work at Stations 16, 26
- Grading at Stations 21, 24
- Form, pour, cure curb and gutter at Stations 21, 28
- Form platform and install snowmelt at Station 24
- City Street Lighting conduit termination at Station 26
- Install electrical cabinet at Station 32
Week of June 27:
- Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24, 26
- Install daily traffic control at Stations 16, 28, 32, 33
- Full lane closure at Station 16
- Construct restroom at Station 1
- Install shelter at Stations 1, 28, 32, 33
- Northbound and Southbound lane closures at Station 13
- Install base course and survey staking at Stations 13, 26
- Form platform at Station 13
- Install snowmelt cable at Stations 13, 24
- Sewer work at Stations 16, 26
- Survey Station 16
- Grading at Stations 16, 24
- Form, pour, cure curb and gutter & install platform ramp snowmelt at Stations 21, 24
- Pour and cure pavement & form and pour platform ramps at Station 21
- Survey staking, pour platform and ramps, and install trench drain at Station 24
- Pour concrete leveling pad at Station 33
Week of July 4:
- Install permanent traffic control at Stations 1, 13, 21, 22, 24, 26
- Install daily traffic control at Stations 16, 28, 32, 33
- Construct restroom at Station 1
- Northbound and Southbound lane closures, install snowmelt cable, form platform, and install trench drain at Station 13
- Survey Station 16
- Grading at Stations 16, 26
- Pour and cure pavement at Station 21
- Pour sidewalk, 12” pavement, and ramps at Station 24
- Install platform conduit at Station 26
East-West Bus Rapid Transit Construction Updates will be updated weekly.
