Construction Update Three-Week Look Ahead June 24, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of June 20:

  • Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24, 26
  • Install daily traffic control at Stations 16, 28, 32, 33
  • Construct restroom and install bollards at Station 1
  • Pour platform ramps and sidewalk at Stations 2, 28
  • Northbound and Southbound lane closures at Station 13
  • Survey Staking at Stations 13, 24, 26
  • Install platform conduit at Stations 13, 24
  • Sewer work at Stations 16, 26
  • Grading at Stations 21, 24
  • Form, pour, cure curb and gutter at Stations 21, 28
  • Form platform and install snowmelt at Station 24
  • City Street Lighting conduit termination at Station 26
  • Install electrical cabinet at Station 32

 

Week of June 27:

  • Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24, 26
  • Install daily traffic control at Stations 16, 28, 32, 33
  • Full lane closure at Station 16
  • Construct restroom at Station 1
  • Install shelter at Stations 1, 28, 32, 33
  • Northbound and Southbound lane closures at Station 13
  • Install base course and survey staking at Stations 13, 26
  • Form platform at Station 13
  • Install snowmelt cable at Stations 13, 24
  • Sewer work at Stations 16, 26
  • Survey Station 16
  • Grading at Stations 16, 24
  • Form, pour, cure curb and gutter & install platform ramp snowmelt at Stations 21, 24
  • Pour and cure pavement & form and pour platform ramps at Station 21
  • Survey staking, pour platform and ramps, and install trench drain at Station 24
  • Pour concrete leveling pad at Station 33

 

Week of July 4:

  • Install permanent traffic control at Stations 1, 13, 21, 22, 24, 26
  • Install daily traffic control at Stations 16, 28, 32, 33
  • Construct restroom at Station 1
  • Northbound and Southbound lane closures, install snowmelt cable, form platform, and install trench drain at Station 13
  • Survey Station 16
  • Grading at Stations 16, 26
  • Pour and cure pavement at Station 21
  • Pour sidewalk, 12” pavement, and ramps at Station 24
  • Install platform conduit at Station 26

East-West Bus Rapid Transit Construction Updates will be updated weekly.