East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.
Week of May 30:
- Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24
- Install daily traffic control at Stations 16, 28, 32, 33
- Construct restroom at Station 1
- Survey staking at Stations 2, 13
- Pour platform at Stations 2, 28
- Install platform conduit, Northbound and Southbound lane closures, and street light work at Station 13
- Survey platform at Stations 21, 28
- Form platform at Station 21
- Grade Stations 21, 32
- Remove concrete, common excavation and subgrade, install base course, City Street Lighting conduit termination & sawcutting at Station 24
- Install snowmelt at Station 28
- Pour platform ramps, install sidewalk, and install 12” red stamped pavement at Station 32
- Install 12” pavement, platform ramp snowmelt, light pole bases, & form and pour platform ramps at Station 33
Week of June 6:
- Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24, 26
- Install daily traffic control at Stations 16, 28, 32, 33
- Construct restroom at Station 1
- Form, pour, and cure curb & gutter at Stations 2, 28
- Pour and cure pavement, form platform ramps, install platform ramp snowmelt, pour platform ramps at Station 2
- Install platform conduits and snowmelt cable & Northbound and Southbound lane closures at Station 13
- Sewer work at Station 16
- Install station snowmelt at Station 21
- Sawcutting at Stations 22, 26
- Remove concrete, common excavation and subgrade, & install base course at Station 22
- City Street Lighting conduit termination at Stations 22, 24
- Survey staking and street light removals at Station 24
- Pour sidewalk at Station 28
- Install 12” pavement at Station 32
- Install sidewalk at Station 33
Week of June 13:
- Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24, 26
- Install daily traffic control at Stations 16, 28, 32, 33
- Construct restroom at Station 1
- Pour and cure pavement at Station 2
- Northbound and Southbound lane closures at Station 13
- Form platform at Stations 13, 24
- Sewer work at Stations 16, 26
- Pour platform, form, pour and cure curb & gutter, form platform ramps, and install platform ramp snowmelt at Station 21
- Grade Stations 21, 24
- Survey staking at Stations 22, 24, 26
- City Street Lighting conduit termination at Stations 22, 26
- Street Light Removals at Station 22
- Install platform conduit at Station 24
- Concrete removals, common excavation and subgrade, & install base course at Station 26
East-West Bus Rapid Transit Construction Updates will be updated weekly.