Construction Update Three-Week Look Ahead May 13, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of May 9:

  • Install permanent traffic control at Stations 1, 2, 13, 21
  • Install daily traffic control at Stations 16, 28, 32, 33
  • Install pavement and sidewalk & construct restroom at Station 1
  • Stake survey at Stations 2, 13
  • Install platform conduit at Station 2
  • Northbound and Southbound lane closures, pave median, install temporary pavement markings, common excavation and subgrade & remove concrete at Station 13
  • Remove concrete pavements at Station 16
  • Survey platform at Stations 28, 32, 33
  • Install conduit at Station 28
  • Install platform conduit at Station 32
  • Grade and form platform at Stations 32, 33
  • Install snowmelt at Station 33

Week of May 16:

  • Install permanent traffic control at Stations 1, 2, 13, 21
  • Install daily traffic control at Stations 16, 28, 32, 33
  • Construct restroom, install sidewalk, and pour ramps at Station 1
  • Install snowmelt at Stations 1, 2, 28, 32, 33
  • Stake survey at Stations 2, 13
  • Install platform conduit at Station 2
  • Grade Stations 2, 28, 33
  • Form platform at Stations 2, 28, 32, 33
  • Northbound and Southbound outside lane closure, sewer work, install base course, and street light work at Station 13
  • Install conduit at Station 28
  • Survey platform at Station 33

Week of May 23:

  • Install permanent traffic control at Stations 1, 2, 13, 21
  • Install daily traffic control at Stations 16, 28, 32, 33
  • Construct restroom at Station 1
  • Stake survey at Stations 2, 13
  • Install snowmelt at Stations 2, 28
  • Pour platform at Stations 2, 28
  • Form, pour, and cure curb and gutter at Stations 2, 28, 32, 33
  • Install pavement at Station 2
  • Northbound and Southbound outside lane closure, street light work, install platform conduits at Station 13
  • Survey Station 16
  • Survey platform and install 12” pavement at Stations 28, 32
  • Grade Station 32
  • Install sidewalk at Station 33