East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.
Week of May 9:
- Install permanent traffic control at Stations 1, 2, 13, 21
- Install daily traffic control at Stations 16, 28, 32, 33
- Install pavement and sidewalk & construct restroom at Station 1
- Stake survey at Stations 2, 13
- Install platform conduit at Station 2
- Northbound and Southbound lane closures, pave median, install temporary pavement markings, common excavation and subgrade & remove concrete at Station 13
- Remove concrete pavements at Station 16
- Survey platform at Stations 28, 32, 33
- Install conduit at Station 28
- Install platform conduit at Station 32
- Grade and form platform at Stations 32, 33
- Install snowmelt at Station 33
Week of May 16:
- Install permanent traffic control at Stations 1, 2, 13, 21
- Install daily traffic control at Stations 16, 28, 32, 33
- Construct restroom, install sidewalk, and pour ramps at Station 1
- Install snowmelt at Stations 1, 2, 28, 32, 33
- Stake survey at Stations 2, 13
- Install platform conduit at Station 2
- Grade Stations 2, 28, 33
- Form platform at Stations 2, 28, 32, 33
- Northbound and Southbound outside lane closure, sewer work, install base course, and street light work at Station 13
- Install conduit at Station 28
- Survey platform at Station 33
Week of May 23:
- Install permanent traffic control at Stations 1, 2, 13, 21
- Install daily traffic control at Stations 16, 28, 32, 33
- Construct restroom at Station 1
- Stake survey at Stations 2, 13
- Install snowmelt at Stations 2, 28
- Pour platform at Stations 2, 28
- Form, pour, and cure curb and gutter at Stations 2, 28, 32, 33
- Install pavement at Station 2
- Northbound and Southbound outside lane closure, street light work, install platform conduits at Station 13
- Survey Station 16
- Survey platform and install 12” pavement at Stations 28, 32
- Grade Station 32
- Install sidewalk at Station 33
East-West Bus Rapid Transit Construction Updates will be updated weekly.