East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.
Week of May 23:
- Install permanent traffic control at Stations 1, 2, 13, 21
- Install daily traffic control at Stations 16, 28, 32, 33
- Construct restroom and pour ramps at Station 1
- Install sidewalk at Stations 1, 33
- Survey staking at Stations 2, 13, 22
- Survey at Station 16
- Survey platform at Stations 21, 28, 32, 33
- Install snowmelt at Stations 2, 28
- Pour platform at Station 2
- Sewer and street light work at Station 13
- Remove pedestrian walkway and install erosion control at Station 22
- Grading at Stations 28, 32
- Form platform at Station 28
- Form, pour, cure curb and gutter at Stations 32, 33
- Install 12″ pavement at Station 32
Week of May 31:
- Install permanent traffic control at Stations 1, 2, 13, 21, 22 and P1
- Install daily traffic control at Stations 16, 28, 32, 33
- Construct restroom at Station 1
- Form, pour, cure curb and gutter at Stations 2, 28
- Pour & cure pavement, form platform ramps, and install snowmelt at Station 2
- Survey staking, street light work, and install platform conduits at Station 13
- Survey & form platform and grading at Station 21
- Install snowmelt at Stations 21, 28
- Saw cutting, concrete removals, common excavation & subgrade, base course installation, and city street lighting conduit termination at Station 22
- Install erosion control and survey staking at Station 24 and P1
- Saw cutting at P1
- Pour platform at Station 28
- Install sidewalk and 12″ pavement at Station 32
- Install sidewalk and form and pour platform ramps at Station 33
Week of June 6:
- Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24 and P1
- Install daily traffic control at Stations 16, 28, 32, 33
- Construct restroom at Station 1
- Pour and cure pavement at Station 2
- Install platform conduits, form platform, and install snowmelt cable at Station 13
- Pour platform, grading, form & pour platform ramps, and install snowmelt at Station 21
- Form, pour, cure curb and gutter at Stations 21, 28
- Concrete removals, common excavation & subgrade, base course installation, and city street lighting conduit termination at Station 24 and P1
- Saw cutting at Station 24
- Install 12″ pavement at Station 28
East-West Bus Rapid Transit Construction Updates will be updated weekly.