Construction Update Three-Week Look Ahead May 27, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of May 23:

  • Install permanent traffic control at Stations 1, 2, 13, 21
  • Install daily traffic control at Stations 16, 28, 32, 33
  • Construct restroom and pour ramps at Station 1
  • Install sidewalk at Stations 1, 33
  • Survey staking at Stations 2, 13, 22
  • Survey at Station 16
  • Survey platform at Stations 21, 28, 32, 33
  • Install snowmelt at Stations 2, 28
  • Pour platform at Station 2
  • Sewer and street light work at Station 13
  • Remove pedestrian walkway and install erosion control at Station 22
  • Grading at Stations 28, 32
  • Form platform at Station 28
  • Form, pour, cure curb and gutter at Stations 32, 33
  • Install 12″ pavement at Station 32

Week of May 31:

  • Install permanent traffic control at Stations 1, 2, 13, 21, 22 and P1
  • Install daily traffic control at Stations 16, 28, 32, 33
  • Construct restroom at Station 1
  • Form, pour, cure curb and gutter at Stations 2, 28
  • Pour & cure pavement, form platform ramps, and install snowmelt at Station 2
  • Survey staking, street light work, and install platform conduits at Station 13
  • Survey & form platform and grading at Station 21
  • Install snowmelt at Stations 21, 28
  • Saw cutting, concrete removals, common excavation & subgrade, base course installation, and city street lighting conduit termination at Station 22
  • Install erosion control and survey staking at Station 24 and P1
  • Saw cutting at P1
  • Pour platform at Station 28
  • Install sidewalk and 12″ pavement at Station 32
  • Install sidewalk and form and pour platform ramps at Station 33

Week of June 6:

  • Install permanent traffic control at Stations 1, 2, 13, 21, 22, 24 and P1
  • Install daily traffic control at Stations 16, 28, 32, 33
  • Construct restroom at Station 1
  • Pour and cure pavement at Station 2
  • Install platform conduits, form platform, and install snowmelt cable at Station 13
  • Pour platform, grading, form & pour platform ramps, and install snowmelt at Station 21
  • Form, pour, cure curb and gutter at Stations 21, 28
  • Concrete removals, common excavation & subgrade, base course installation, and city street lighting conduit termination at Station 24 and P1
  • Saw cutting at Station 24
  • Install 12″ pavement at Station 28

East-West Bus Rapid Transit Construction Updates will be updated weekly.

construction-map-with-stations