East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below:
Week of Sept. 27:
- Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17, 18, 19, 20
- Backfill, restore and open roadway at Stations 3, 4
- Install sidewalk at Stations 5, 6, 7, 8
- Install base at Station 5
- Install 12” Pavement at Stations 5, 7, 8
- Install ramp and steps, form and pour curb and gutter, install snowmelt, pull boxes and grounding ring and snowmelt inspection at Stations 7, 8, 9
- Survey Stations 8, 10, 11, 12
- Install conduit at Stations 12, 17, 19
- Regrade and form platform at Station 12
- Conduit inspection and install sewer at Station 17
- Relocate street light at Stations 18, 19
- Common excavation, base course installation and concrete pavement removal at Station 20
Week of Oct. 4:
- Install permanent traffic control at Stations 1, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17, 18, 19, 20
- Install 12” pavement at Station 5
- Backfill and restoration at Stations 5, 7, 8
- Open roadway at Station 6
- Install sidewalk at Stations 7, 8, 9, 10
- Install 12” pavement at Stations 7, 8, 9
- Form and pour curb and gutter at Stations 9, 10
- Install snowmelt, pull boxes and grounding ring at Stations 10, 11, 12, 17, 19
- Snowmelt inspection at Stations 10, 11, 12, 17
- Install ramp and steps at Station 10
- Form platform at Stations 11, 12, 17, 19
- Pour platform at Stations 11, 12
- Survey and grading at Station 12
- Common excavation and concrete pavement removal at Station 15
- Survey platform and install base course at Stations 15, 20
- Install conduit at Stations 15, 18, 19
- Regrade Stations 17, 19
- Relocate street light at Station 18
- Boring for street lights at Station 20
Week of Oct. 11:
- Install permanent traffic control at Stations 1, 5, 7, 8, 9, 10, 11, 12, 14, 15, 17, 18, 19, 20, 21
- Install daily traffic control at Stations 3, 4, 6
- Pavement marking removal and replacement at Stations 3, 4, 5, 6
- Open roadway at Stations 5, 7, 8, 9
- Backfill and restoration at Station 9
- Install sidewalk and 12” pavement at Stations 10, 11, 12
- Survey Stations 11, 12, 17, 19
- Grading and form and pour curb and gutter at Stations 11, 12
- Install ramp and steps at Stations 11, 12, 17, 19
- Install snowmelt, pull boxes and grounding ring at Stations 12, 15, 17, 18, 19
- Snowmelt inspection at Stations 12, 17, 18, 19
- Install conduit at Stations 15, 20
- Regrade Stations 15, 17, 18, 19
- Form platform at Stations 15, 18
- Pour platform and form and pour curb and gutter at Stations 17, 19
- Install sidewalk at Station 17
- Boring for street lights at Stations 20, 21
- Common excavation, base course installation, survey platform and concrete pavement removal at Station 21
East-West Bus Rapid Transit Construction Updates will be updated weekly.