Construction Update Three-Week Look Ahead October 21, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of October 17:

  • Install permanent traffic control at Stations 1, 27
  • Install daily traffic control at Stations 19, 22, 30, 31
  • Restoration at Stations 1, 16
  • Install platform conduit at Stations 19, 27
  • Adjust pull boxes and install platform ramp snowmelt at Station 22
  • Grading at Station 27
  • Form, pour, cure curb and gutter & pour 12” pavement at Station 30
  • Install snowmelt at Station 31

Week of October 24:

  • Install permanent traffic control at Stations 1, 27
  • Install daily traffic control at Stations 19, 22, 25, 30, 31
  • Restoration at Stations 1, 16
  • Pour 12” pavement at Station 19
  • Pour ramps and sidewalk at Stations 22, 30
  • Form platform at Station 27
  • Install snowmelt at Stations 27, 31
  • Form ramps and install snowmelt ramps at Station 30
  • Pour platform and grading at Station 31

Week of October 31:

  • Install permanent traffic control at Station 27
  • Install daily traffic control at Stations 30, 31
  • Grading at Stations 27, 31
  • Form, pour, cure curb and gutter, pour 12” pavement, form ramps & install snowmelt ramps at Station 31

East-West Bus Rapid Transit Construction Updates will be updated weekly.