East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.
Week of Oct. 18:
- Install permanent traffic control at Stations 1, 6, 8, 9, 10, 11, 12, 14, 15, 17, 18, 19, 20
- Install daily traffic control at Stations 6, 7
- Backfill and restoration at Stations 3, 7, 9
- Median pavement removal and concrete work at Station 6
- Survey Stations 6, 11, 12, 17, 18
- Pavement removal and concrete work at Station 6
- Install City of Wauwatosa conduits at Station 6
- Open roadway at Stations 8, 9, 10
- Install sidewalk at Stations 10, 11
- Pour platform at Station 11
- Form and pour curb and gutter at Stations 11, 12
- Install 12” pavement at Station 11
- Install snowmelt, pull boxes and grounding ring at Stations 12, 19
- Install driveway, ramp and steps, snowmelt inspection and grading at Station 12
- Survey platform at Stations 14, 15, 19, 20
- Install conduit at Stations 14, 17, 20
- Regrade Stations 14, 17, 19
- Sewer and install base course at Station 15
- Form platform at Stations 17, 19
- Street light termination at Stations 18, 20
- Install sewer at Station 19
Week of Oct. 25:
- Install permanent traffic control at Stations 1, 6, 11, 12, 14, 15, 17, 18, 19, 20
- Install daily traffic control at Station 10
- Additional trench drain at Station 4
- Median Pavement Concrete work at Station 6
- Backfill and restoration at Stations 10, 11
- Install driveways, 12” pavement and sidewalk at Station 12
- Form platform at Stations 14, 15, 20
- Install snowmelt, pull boxes and grounding ring at Stations 14, 15, 17, 19, 20
- Snowmelt inspection and pour platform at Stations 14, 17, 19
- Grading at Station 14
- Install conduit at Stations 15, 18, 20
- Regrade at Stations 15, 17, 18, 19, 20
- Survey at Stations 17, 18
- Install ramp and steps at Station 17
- Trenchdrain at Station 19
- Install ramp and steps at Station 20
Week of Nov. 1:
- Install permanent traffic control at Stations 1, 6, 11, 12, 14, 15, 17, 18, 19, 20
- Restroom construction at Station 1
- Open roadway at Stations 6, 11, 12
- Install snowmelt, pull boxes and grounding ring at Stations 14, 15, 17, 18, 19, 20
- Snowmelt inspection at Stations 14, 17, 18, 20
- Survey Stations 14, 15, 19, 20
- Install ramp and steps at Stations 14, 15, 17, 19
- Form and pour curb and gutter, install sidewalk and 12” pavement at Stations 14, 17, 19
- Pour platform at Stations 15, 18, 20
- Grading at Stations 15, 20
- Regrade, trenchdrain and form platform at Station 18
East-West Bus Rapid Transit Construction Updates will be updated weekly.