East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below:
Week of Oct. 4:
- Install permanent traffic control at Stations 1, 5, 7, 8, 9, 10, 11, 12, 14, 15, 17, 18, 19, 20
- Backfill and restoration at Stations 3, 4, 5
- Install sidewalk at Stations 5, 7, 8
- Install 12” pavement at Stations 5, 7, 8, 9
- Form and pour curb and gutter at Station 7, 9, 10
- Install snowmelt, pull boxes and grounding ring at Stations 9, 10, 11, 12
- Snowmelt inspection at Stations 9, 10, 11
- Install ramp and steps at Stations 9, 10
- Form platform at Station 11, 12
- Sewer work at Station 12
- Street lighting terminations at Station 14, 15, 19
- Install sewer at Station 14, 17
- common excavation and concrete pavement removal at Station 15
- Install base course at Station 15, 20
- Signal work at Station 17
- Relocate street lights at Station 18, 19
- Install conduit at Station 19
Week of Oct. 11:
- Install permanent traffic control at Stations 1, 5, 7, 8, 9, 10, 11, 12, 14, 15, 17, 18, 19, 20
- Open roadway at Station 5, 7, 8, 9
- Install sidewalk at Station 6, 9, 10
- Median pavement removals and concrete work at Station 6
- Backfill and restoration at Station 7, 8
- Install 12” pavement at Station 9, 10
- Form and pour curb and gutter at Station 10, 11
- Install snowmelt, pull boxes and grounding ring and snowmelt inspection at Station 11, 12, 19
- Pour platform, survey and grading at Station 11, 12
- Install ramp and steps at Station 11
- Water main work at Station 14
- Survey platform at Station 14, 15
- Install conduit at Station 14, 15, 17
- Regrade Station 15, 17, 18, 19
- Form platform at Station 15, 17, 19
- Signal work at Station 17
- Relocate street lights at Station 18
- Terminate street lights at Station 18, 20
- Street lighting at Station 20
Week of Oct. 18:
- Install permanent traffic control at Stations 1, 10, 11, 12, 14, 15, 17, 18, 19, 20
- Restroom construction at Station 1
- Install sidewalk at Station 6, 10, 11, 12
- Median pavement removals and concrete work at Station 6
- Open roadway at Station 10
- Install snowmelt, pull boxes and grounding ring at Station 11, 12, 14, 15, 17, 18
- Snowmelt inspection at Station 11, 12, 14, 15, 17, 18
- Form and pour curb and gutter and install ramp and steps at Station 11, 12, 19
- Install 12” pavement at Station 11, 12
- Install conduit at Station 14
- Regrade Station 14, 18, 19, 20
- Form platform at Station 14, 18
- Pour platform at Station 15, 17, 18, 19
- Survey Station 19
- Terminate street lights and install conduit at Station 20
East-West Bus Rapid Transit Construction Updates will be updated weekly.