East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below:
Week of Sept. 13:
- Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17, 18, 19
- Install daily traffic control at Stations 20, 21
- Form and pour curb and gutter and install sidewalk at Stations 3, 4, 5, 6
- Install 12” pavement at Stations 3, 4
- Ramp re-work at Station 4
- Install ramp, steps and manhole adjustment at Station 5
- Survey Stations 7, 9
- Install trenchdrain at Stations 7, 10
- Install drain pipe at Station 7
- Form platform at Stations 8, 14
- Install snowmelt, pull boxes and grounding ring at Stations 8, 10
- Pour platform and install grading at Stations 9, 10
- Install conduit at Stations 12, 14, 17
- Regrade Stations 12, 14
- Install temporary street lighting at Station 15
- Common excavation and remove concrete pavement at Stations 17, 18, 19
- Survey platform at Stations 17, 18
- Install base course at Station 18
- Sawcutting at Stations 20, 21
Week of Sept. 20:
- Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17, 18, 19, 20
- Install 12” pavement at Stations 3, 4, 5, 6
- Install snowmelt, pull boxes and grounding ring and snowmelt inspection at Stations 7, 8, 9, 11, 12, 14
- Install ramp and steps and form and pour curb and gutter at Stations 7, 8, 9
- Install sidewalk at Stations 7, 9
- Pour platform at Stations 8, 12, 14
- Survey Station 8
- Grading at Stations 8, 10
- Install and connect trenchdrain and survey Station 10
- Form platform at Stations 11, 12, 17, 18
- Survey platform at Stations 12, 19
- Remove concrete pavement at Stations 15, 20
- Common excavation at Stations 15, 19, 20
- Install conduit at Stations 17, 18, 19
- Regrade Stations 17, 18
- Conduit inspection at Station 17
- Install base course at Station 19
Week of Sept. 27:
- Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17, 18, 19, 20, 21
- Backfill and restoration and open roadway at Stations 3, 4, 5, 6
- Install 12” Pavement at Stations 7, 8, 9, 10
- Snowmelt inspection at Stations 8, 10, 12, 17, 18, 19
- Install ramp and steps at Stations 8, 10, 11, 12
- Install sidewalk at Stations 8, 9, 10, 12
- Install snowmelt, pull boxes and grounding ring at Stations 10, 12, 17, 18, 19
- Form and pour curb and gutter at Stations 10, 11, 12
- Pour platform at Stations 11, 17, 18
- Survey Station 11
- Grading at Stations 11, 12
- Install base course and conduit at Stations 15, 20
- Survey platform at Stations 15, 17, 20
- Regrade Stations 17, 19
- Form platform at Station 19
- Common excavation at Stations 20, 21
- Remove concrete pavement at Station 21
East-West Bus Rapid Transit Construction Updates will be updated weekly.