Week of Sept. 13:

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17, 18, 19
  • Install daily traffic control at Stations 20, 21
  • Form and pour curb and gutter and install sidewalk at Stations 3, 4, 5, 6
  • Install 12” pavement at Stations 3, 4
  • Ramp re-work at Station 4
  • Install ramp, steps and manhole adjustment at Station 5
  • Survey Stations 7, 9
  • Install trenchdrain at Stations 7, 10
  • Install drain pipe at Station 7
  • Form platform at Stations 8, 14
  • Install snowmelt, pull boxes and grounding ring at Stations 8, 10
  • Pour platform and install grading at Stations 9, 10
  • Install conduit at Stations 12, 14, 17
  • Regrade Stations 12, 14
  • Install temporary street lighting at Station 15
  • Common excavation and remove concrete pavement at Stations 17, 18, 19
  • Survey platform at Stations 17, 18
  • Install base course at Station 18
  • Sawcutting at Stations 20, 21

Week of Sept. 20:

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17, 18, 19, 20
  • Install 12” pavement at Stations 3, 4, 5, 6
  • Install snowmelt, pull boxes and grounding ring and snowmelt inspection at Stations 7, 8, 9, 11, 12, 14
  • Install ramp and steps and form and pour curb and gutter at Stations 7, 8, 9
  • Install sidewalk at Stations 7, 9
  • Pour platform at Stations 8, 12, 14
  • Survey Station 8
  • Grading at Stations 8, 10
  • Install and connect trenchdrain and survey Station 10
  • Form platform at Stations 11, 12, 17, 18
  • Survey platform at Stations 12, 19
  • Remove concrete pavement at Stations 15, 20
  • Common excavation at Stations 15, 19, 20
  • Install conduit at Stations 17, 18, 19
  • Regrade Stations 17, 18
  • Conduit inspection at Station 17
  • Install base course at Station 19

Week of Sept. 27:

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17, 18, 19, 20, 21
  • Backfill and restoration and open roadway at Stations 3, 4, 5, 6
  • Install 12” Pavement at Stations 7, 8, 9, 10
  • Snowmelt inspection at Stations 8, 10, 12, 17, 18, 19
  • Install ramp and steps at Stations 8, 10, 11, 12
  • Install sidewalk at Stations 8, 9, 10, 12
  • Install snowmelt, pull boxes and grounding ring at Stations 10, 12, 17, 18, 19
  • Form and pour curb and gutter at Stations 10, 11, 12
  • Pour platform at Stations 11, 17, 18
  • Survey Station 11
  • Grading at Stations 11, 12
  • Install base course and conduit at Stations 15, 20
  • Survey platform at Stations 15, 17, 20
  • Regrade Stations 17, 19
  • Form platform at Station 19
  • Common excavation at Stations 20, 21
  • Remove concrete pavement at Station 21