Construction Update Three-Week Look Ahead September 2, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

 

Week of August 29:

  • Install permanent traffic control at Stations 1, 13, 22, 26
  • Install daily traffic control at Stations 16, 23, 25, 27, 30, 31
  • Pour sidewalk at Stations 13, 26
  • Install snowmelt cables and pour platform at Station 16
  • Form, pour, cure curb and gutter at Stations 23, 25
  • Install platform ramp snowmelt at Stations 23, 26
  • Form ramps at Station 23
  • Pour 12” pavement at Station 25
  • Remove concrete at Stations 26, 31
  • Common excavation and subgrade, install base course, & sewer work at Station 26
  • Stump grinding at Stations 27, 30, 31
  • Remove street lights and install platform conduit at Station 30

Week of September 6:

  • Install permanent traffic control at Stations 1, 13, 22, 26
  • Install daily traffic control at Stations 16, 23, 25, 27, 30, 31
  • Survey Station 16
  • Grade Stations 16, 22
  • Install platform conduit at Stations 22, 30
  • Pour 12” pavement at Stations 23, 26
  • Form and pour sidewalk at Station 23
  • Install platform ramp snowmelt at Stations 23, 25
  • Pour ramps and sidewalk at Station 25
  • Form, pour, cure curb and gutter & sewer work at Station 26
  • Survey staking, install erosion control, sawcutting, and remove concrete at Station 27
  • Common excavation and subgrade at Stations 27, 31
  • Install base course at Station 31

Week of September 12:

  • Install permanent traffic control at Stations 1, 13, 22, 26
  • Install daily traffic control at Stations 16, 23, 25, 27, 30, 31
  • Prep and install overhead charger at Station 1
  • Form, pour, cure curb and gutter at Station 16
  • Pour 12” pavement at Stations 16, 26
  • Form platform and install snowmelt system at Stations 22, 30
  • Survey staking, remove concrete, common excavation and subgrade, & install base course at Station 27
  • Grade Stations 27, 30
  • Remove street lights and install platform conduit at Station 31

East-West Bus Rapid Transit Construction Updates will be updated weekly.