East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below:
Week of Aug. 30:
- Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14
- Install daily traffic control at Stations 17, 18, 19
- Install snowmelt, pull boxes, and grounding ring at Stations 3, 4, 6, 7, 9
- Snowmelt inspection at Stations 3, 4, 6, 7
- Form and pour curb and gutter and install ramp and steps at Stations 3, 4, 6
- Install trenchdrain, drain pipe, and grading at Station 5
- Manhole adjustment at Stations 5, 10
- Pour platform at Station 6
- Form platform at Stations 7, 9, 10
- Install conduit at Station 8
- Regrade Stations 8, 9, 10
- Common excavation, concrete pavement removal, and install base course at Station 12
- Survey platform and install curb, sidewalk, and pavement at Station 14
- Install inlet protection at Stations 17, 18, 19, 20, 21
- Sawcutting at Stations 17, 18, 19
Week of Sept. 7:
- Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15
- Install daily traffic control at Stations 20, 21
- Install sidewalk at Stations 3, 4, 5, 6
- Install 12” pavement at Stations 3, 4, 6
- Install snowmelt, pull boxes, and grounding ring at Stations 5, 8, 9, 10, 11
- Snowmelt inspection at Stations 5, 9, 10
- Form and pour curb and gutter and install ramp and steps at Station 5
- Install catch basin adjustments at Station 6
- Pour platform at Stations 7, 9, 10
- Grading at Station 7
- Survey Stations 7, 9
- Install trenchdrain and drain pipe at Station 7
- Survey platform at Stations 8, 12, 14
- Form platform at Stations 8, 11
- Regrade Station 11
- Install conduit at Station 12
- Install sewer at Station 14
- Common excavation and concrete pavement removal at Station 15
- Sawcutting at Stations 20, 21
Week of Sept. 13:
- Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15
- Backfill and restoration at Stations 3, 4, 6
- Install 12” pavement at Station 5
- Install snowmelt, pull boxes, and grounding ring at Stations 7, 9, 10, 11, 12
- Snowmelt inspection at Stations 7, 8, 9, 10, 11, 12
- Form and pour curb and gutter at Stations 7, 8, 9, 10
- Install ramp and steps at Stations 7, 8, 9, 10
- Install sidewalk at Stations 7, 9
- Install 12” pavement at Station 7
- Pour platform at Stations 8, 11
- Survey Stations 8, 10, 11
- Grading at Stations 8, 9, 10, 11
- Regrade and form platform at Stations 12, 14
- Install conduit at Stations 14, 15, 17
- Common excavation, install base course, and survey platform at Stations 15, 17
- Concrete pavement removal at Station 17
East-West Bus Rapid Transit Construction Updates will be updated weekly.