Week of Aug. 30:

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14
  • Install daily traffic control at Stations 17, 18, 19
  • Install snowmelt, pull boxes, and grounding ring at Stations 3, 4, 6, 7, 9
  • Snowmelt inspection at Stations 3, 4, 6, 7
  • Form and pour curb and gutter and install ramp and steps at Stations 3, 4, 6
  • Install trenchdrain, drain pipe, and grading at Station 5
  • Manhole adjustment at Stations 5, 10
  • Pour platform at Station 6
  • Form platform at Stations 7, 9, 10
  • Install conduit at Station 8
  • Regrade Stations 8, 9, 10
  • Common excavation, concrete pavement removal, and install base course at Station 12
  • Survey platform and install curb, sidewalk, and pavement at Station 14
  • Install inlet protection at Stations 17, 18, 19, 20, 21
  • Sawcutting at Stations 17, 18, 19

Week of Sept. 7:

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15
  • Install daily traffic control at Stations 20, 21
  • Install sidewalk at Stations 3, 4, 5, 6
  • Install 12” pavement at Stations 3, 4, 6
  • Install snowmelt, pull boxes, and grounding ring at Stations 5, 8, 9, 10, 11
  • Snowmelt inspection at Stations 5, 9, 10
  • Form and pour curb and gutter and install ramp and steps at Station 5
  • Install catch basin adjustments at Station 6
  • Pour platform at Stations 7, 9, 10
  • Grading at Station 7
  • Survey Stations 7, 9
  • Install trenchdrain and drain pipe at Station 7
  • Survey platform at Stations 8, 12, 14
  • Form platform at Stations 8, 11
  • Regrade Station 11
  • Install conduit at Station 12
  • Install sewer at Station 14
  • Common excavation and concrete pavement removal at Station 15
  • Sawcutting at Stations 20, 21

Week of Sept. 13:

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15
  • Backfill and restoration at Stations 3, 4, 6
  • Install 12” pavement at Station 5
  • Install snowmelt, pull boxes, and grounding ring at Stations 7, 9, 10, 11, 12
  • Snowmelt inspection at Stations 7, 8, 9, 10, 11, 12
  • Form and pour curb and gutter at Stations 7, 8, 9, 10
  • Install ramp and steps at Stations 7, 8, 9, 10
  • Install sidewalk at Stations 7, 9
  • Install 12” pavement at Station 7
  • Pour platform at Stations 8, 11
  • Survey Stations 8, 10, 11
  • Grading at Stations 8, 9, 10, 11
  • Regrade and form platform at Stations 12, 14
  • Install conduit at Stations 14, 15, 17
  • Common excavation, install base course, and survey platform at Stations 15, 17
  • Concrete pavement removal at Station 17