East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.
Week of September 26:
·
Install permanent traffic control at Stations 1,
13, 22, 27
·
Install daily traffic control at Stations 16,
23, 24, 25, 26, 30, 31
·
Install City Street Light Connection at Station
13
·
Form, pour, cure curb and gutter at Stations 13,
22
·
Grade Stations 16, 22, 30
·
Pour ramps and sidewalk at Station 16
·
Survey staking at Stations 22, 30, 31
·
Pour platform at Station 22
·
Set shelter at Stations 23, 24, 25, 26
·
Adjust conduit, form platform, and install
snowmelt at Station 30
·
Install platform conduit at Station 31
Week of October 3:
·
Install permanent traffic control at Stations 1,
22, 27
·
Install daily traffic control at Stations 16,
30, 31
·
Form, pour, cure curb & gutter, install 12”
pavement, form ramps, install platform ramp snowmelt, and pour sidewalk at
Station 22
·
Remove street lights and install platform
conduit at Station 27
·
Install snowmelt at Stations 30, 31
·
Pour platform and install trench drain at
Station 30
·
Grade and form platform at Station 31
Week of October 10:
·
Install permanent traffic control at Stations 1,
22, 27
·
Install daily traffic control at Stations 30, 31
·
Pour ramps and sidewalk at Station 22
·
Grade Stations 27, 30, 31
·
Install platform conduit and form platform at
Station 27
·
Install snowmelt at Stations 27, 31
·
Survey staking, pour 12” pavement, and install
trench drain at Station 30
·
Form, pour, cure curb and gutter at Stations 30,
31
East-West Bus