Week of September 26:

·         Install permanent traffic control at Stations 1, 13, 22, 27

·         Install daily traffic control at Stations 16, 23, 24, 25, 26, 30, 31

·         Install City Street Light Connection at Station 13

·         Form, pour, cure curb and gutter at Stations 13, 22

·         Grade Stations 16, 22, 30

·         Pour ramps and sidewalk at Station 16

·         Survey staking at Stations 22, 30, 31

·         Pour platform at Station 22

·         Set shelter at Stations 23, 24, 25, 26

·         Adjust conduit, form platform, and install snowmelt at Station 30

·         Install platform conduit at Station 31

 

Week of October 3:

·         Install permanent traffic control at Stations 1, 22, 27

·         Install daily traffic control at Stations 16, 30, 31

·         Form, pour, cure curb & gutter, install 12” pavement, form ramps, install platform ramp snowmelt, and pour sidewalk at Station 22

·         Remove street lights and install platform conduit at Station 27

·         Install snowmelt at Stations 30, 31

·         Pour platform and install trench drain at Station 30

·         Grade and form platform at Station 31

 

Week of October 10:

·         Install permanent traffic control at Stations 1, 22, 27

·         Install daily traffic control at Stations 30, 31

·         Pour ramps and sidewalk at Station 22

·         Grade Stations 27, 30, 31

·         Install platform conduit and form platform at Station 27

·         Install snowmelt at Stations 27, 31

·         Survey staking, pour 12” pavement, and install trench drain at Station 30

·         Form, pour, cure curb and gutter at Stations 30, 31

 