East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.
Week of September 5:
- Install permanent traffic control at Stations 1, 13, 22, 27
- Install daily traffic control at Stations 16, 23, 25, 26, 30, 31
- Survey and grade Station 16
- Restoration at Station 13
- Install platform conduit at Stations 22, 30
- Pour 12” pavement at Stations 23, 26
- Install platform ramp snowmelt and pour sidewalk at Station 25
- Install base course at Stations 26, 31
- Sewer work at Station 26
- Survey staking at Stations 27, 30
- Install erosion control and sawcutting at Station 27
- Common excavation and subgrade at Station 31
Week of September 12:
- Install permanent traffic control at Stations 1, 13, 22, 27
- Install daily traffic control at Stations 16, 23, 25, 26, 30, 31
- Overhead charger prep and install at Station 1
- Form, pour, cure curb and gutter & pour 12” pavement at Stations 16, 26
- Install platform conduit at Station 22
- Grade Stations 22, 27, 30
- Form platform and install snowmelt system at Stations 22, 30
- Form and pour sidewalk & install platform ramp snowmelt at Station 23
- Form ramps at Station 25
- Sewer work at Stations 26, 31
- Survey staking at Stations 27, 31
- Remove concrete, common excavation and subgrade & install base course at Station 27
- Remove street lights at Station 31
Week of September 19:
- Install permanent traffic control at Stations 1, 13, 22, 27
- Install daily traffic control at Stations 16, 23, 25, 30, 31
- Restoration & form, pour, cure curb and gutter at Station 13
- Install platform ramp snowmelt, form ramps, and pour ramps at Station 16
- Grade and pour platform at Stations 22, 30
- Install snowmelt system at Station 22
- Remove street lights at Station 27
- Survey staking at Station 30
- Install platform conduit and form platform at Station 31
East-West Bus Rapid Transit Construction Updates will be updated weekly.