Construction Update Three-Week Look Ahead August 27, 2021

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below: 

Week of Aug. 23:
  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 14, 15
  • Grade and pave parking lot strip at Station 1
  • Grading at Stations 3, 4
  • Survey Stations 3, 4, 5, 6
  • Pour platform at Stations 4, 5
  • Install snowmelt, pull boxes and grounding ring at Stations 5, 6, 7
  • Install trenchdrain at Station 5
  • Snowmelt inspection at Station 6
  • Regrade Stations 7, 8, 9, 10
  • Form platform at Station 7
  • Install conduit at Stations 8, 10, 11
  • Survey platform at Stations 8, 11, 14
  • Common excavation, remove concrete pavement and install base course at Stations 14, 15
  • Install pull boxes at Stations 16, 17
Week of Aug. 30:
  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15
  • Install daily traffic control at Stations 17, 18, 19
  • Install snowmelt, pull boxes, and grounding ring at Stations 3, 4, 5, 6, 7, 8, 9
  • Form and pour curb and gutter at Stations 3, 4, 5, 6, 7
  • Install ramp and steps at Stations 3, 4, 5, 6, 7
  • Install sidewalk and 12” pavement at Stations 3, 4, 5
  • Install trenchdrain at Station 5
  • Manhole adjustment at Station 5
  • Grading at Stations 5, 6, 7
  • Pour platform at Stations 6, 8
  • Catch basin adjustments at Station 6
  • Snowmelt inspection at Stations 7, 8, 9
  • Pour platform at Station 7
  • Form platform at Stations 8, 9, 10
  • Regrade Station 11
  • Common excavation, remove concrete pavement and install base course at Station 12
  • Survey platform at Stations 12, 15
  • Install conduit at Stations 12, 14, 15
  • Install inlet protection at Stations 17, 18, 19, 20, 21
  • Sawcutting at Stations 17, 18, 19
Week of Sept. 7:
  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15
  • Install daily traffic control at Stations 20, 21
  • Install sidewalk at Stations 6, 7, 8
  • Install 12” pavement at Stations 6, 7
  • Install snowmelt, pull boxes and grounding ring at Stations 7, 10, 11
  • Form/pour/cure curb and gutter at Stations 7, 8, 9
  • Install ramp and steps at Stations 7, 8, 9
  • Survey platform at Station 8
  • Grading at Stations 8, 9
  • Pour platform at Stations 9, 10
  • Survey Station 9
  • Snowmelt inspection at Station 10, 11
  • Form platform at Stations 11, 12
  • Regrade Stations 12, 14, 15
  • Sawcutting at Stations 20, 21