Construction Update Three-Week Look Ahead August 12, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of August 8:

  • Install permanent traffic control at Stations 1, 13, 24, 25, 26
  • Install daily traffic control at Stations 16, 23, 30
  • Install platform conduit at Station 16
  • Install shelter glass at Station 21
  • Survey staking at Stations 23, 25, 30
  • Remove street light at Stations 23, 30
  • Install platform conduit at Station 23
  • Install snowmelt and sidewalk at Station 25
  • Form and pour curb and gutter & pour 12” pavement at Stations 25, 26
  • Install trench drain and form ramps at Station 26
  • Common excavation and subgrade, remove concrete, & install base course at Station 30

Week of August 15:

  • Install permanent traffic control at Stations 1, 13, 24, 26
  • Install daily traffic control at Stations 16, 23, 25, 30
  • Pour sidewalk at Stations 13, 26
  • Form platform and install snowmelt cables at Station 16
  • Remove concrete at Station 23
  • Install platform conduit at Stations 23, 30
  • Pour 12” pavement at Stations 24, 25, 26
  • Install base course, pour platform, & form and pour curb and gutter at Station 25
  • Install trench drain, install platform ramp snowmelt, and pour ramps at Station 26

Week of August 22:

  • Install permanent traffic control at Stations 1, 13, 26
  • Install daily traffic control at Stations 16, 23, 25, 30
  • Remove temporary asphalt, reconnect conduit, & form and pour curb and gutter at Station 13
  • Install snowmelt cables and pour platform at Stations 16, 23
  • Form, pour, and cure curb and gutter & grade at Station 16
  • Survey staking and form platform at Station 23
  • Pour 12” pavement at Station 25
  • Stump grinding, form platform, and install snowmelt at Station 30  

East-West Bus Rapid Transit Construction Updates will be updated weekly.