Week of Aug 16:
- Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11
- Install daily traffic control at Stations 12, 13, 14, 15
- Install snowmelt, pull boxes and grounding ring at Stations 3, 4, 5
- Snowmelt inspection at Stations 3, 4, 5
- Pour platform at Stations 3, 4
- Form platform at Station 6
- Install We-Energies/City Electric conduit at Station 8
- Install conduit at Stations 9, 10
- Install base course at Station 11
- Survey platform at Stations 8, 11
- Sawcutting at Stations 12, 13, 14, 15
Week of Aug 23:
- Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 14, 15
- Grading at Stations 3, 4, 5
- Form and pour curb and gutter, install ramp and steps, install sidewalk, and install 12” pavement at Stations 3, 4
- Pour platform at Stations 4, 5, 6
- Install trenchdrain at Station 5
- Install snowmelt, pull boxes and grounding ring at Stations 6, 7
- Snowmelt inspection at Stations 6, 7
- Regrade at Stations 7, 8, 9, 10, 11
- Form platform at Stations 7, 8
- Install conduit at Stations 8, 11
- Remove concrete pavement, common excavation and install base course at Stations 14, 15
Week of Aug 30:
- Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15
- Install daily traffic control at Stations 17, 18, 19, 20, 21
- Backfill and restoration at Stations 3, 4
- Form and pour curb and gutter at Stations 5, 6, 7
- Install ramp and steps at Stations 5, 6, 7
- Install sidewalk at Stations 5, 6
- Install 12” pavement at Stations 5, 6
- Grading at Stations 6, 7
- Pour platform at Station 7, 8
- Form platform at Stations 8, 9, 10
- Install snowmelt, pull boxes and grounding ring at Stations 8, 9
- Inspect snowmelt at Stations 8, 9
- Remove concrete pavement, common excavation, and install base course at Station 12
- Sawcutting at Stations 17, 18, 19, 20, 21