Construction Update Three-Week Look Ahead December 2, 2022

Construction Update
Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of November 28:

·       Install traffic control at Stations 22, 27, 30,31 

·       Set electrical cabinet at Stations 6, 7, 20

·       Set shelter at Stations 22, 27, 30, 31

Week of December 5:

·       Install traffic control at Stations 22, 27, 30, 31 

·       Set shelter glass at Stations 22, 30

·       Set shelter at Station 27 

 