Week of July 19:
- Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8
- Install Vapor Barrier at Station 1
- Backfill at Station 1
- Install Vault at Station 7
- Regrade at Station 7
- Survey Platform at Station 7
- Redo Boring at Station 7
- Install sewer and adjust water at Station 8
Week of July 26:
- Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8
- Install Conduit at Stations 7, 8
- Install Survey Platform at Station 8
Week of August 2:
- Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8