Construction Update Three-Week Look Ahead May 6, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of May 2:

  • Install permanent traffic control at Stations 1, 2, 13, 21
  • Install daily traffic control at Stations 16, 20, 28, 32, 33
  • Construct restroom, stake survey, pour platform, install pavement & form, pour, and cure curb and gutter at Station 1
  • Sawcut, remove concrete pavement, common excavation and subgrade, and install base course at Station 2
  • Restore Station 8
  • Northbound and Southbound inside lane closure, remove median, and install median stone at Station 13
  • Install sidewalk at Station 20
  • Install conduit at Stations 21, 33
  • Survey platform at Stations 28, 32, 33
  • Remove electrical at Station 28
  • Install street light conduit and curb ramp at Station 32
  • Relocate City Street Lighting and install curb ramp at Station 33

Week of May 9:

  • Install permanent traffic control at Stations 1, 2, 13, 21
  • Install daily traffic control at Stations 16, 20, 28, 32, 33
  • Construct restroom, install pavement, and install sidewalk at Station 1
  • Stake survey at Stations 2, 13
  • Install platform conduit at Station 2
  • Grade Stations 2, 32, 33
  • Restore Station 8
  • Alternating Northbound and Southbound lane closures, pave median, install temporary pavement markings, common excavation and subgrade Station 13
  • Concrete removals at Stations 13, 16
  • Survey Station 16
  • Install streetlights at Station 20
  • Remove electrical at Station 28
  • Install platform conduit at Station 32
  • Form platform at Stations 32, 33
  • Install conduit and snowmelt cable at Station 33

Week of May 16:

  • Install permanent traffic control at Stations 1, 2, 13, 21
  • Install daily traffic control at Stations 16, 28, 32, 33
  • Full lane closure at Station 16
  • Construct restroom at Station 1
  • Form platform at Stations 2, 32, 33
  • Install snowmelt and pour platform at Station 2
  • Northbound and Southbound outside lane closure, install platform conduit, and stake survey at Station 13
  • Sewer work and install base course at Stations 13, 16
  • Common excavation and subgrade Station 16
  • Install snowmelt cable and grade Stations 32, 33

East-West Bus Rapid Transit Construction Updates will be updated weekly.