Construction Update Three-Week Look Ahead November 11, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of November 7:

  • Install permanent traffic control at Stations 22, 27
  • Install daily traffic control at Stations 23, 30, 31
  • Pour sidewalk at Stations 22, 23, 30, 31
  • Grading at Stations 27, 30
  • Form and pour curb and gutter & form platform ramps at Station 27
  • Pour 12” pavement at Stations 27, 31
  • Install and pour snowmelt ramps at Station 30

Week of November 14:

  • Install permanent traffic control at Stations 22, 27
  • Install daily traffic control at Stations 16, 23, 30, 31
  • Restoration at Stations 1, 16, 23
  • Pour 12” pavement at Station 27
  • Install and pour snowmelt platform ramps at Stations 27, 31
  • Pour sidewalk at Stations 27, 30, 31
  • Form ramps at Station 31

Week of November 21:

  • Install permanent traffic control at Stations 22, 27
  • Install daily traffic control at Station 31
  • Pour sidewalk at Stations 27, 31

East-West Bus Rapid Transit Construction Updates will be updated weekly.

Construction Map with Stations July 9, 2021