East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.
Week of November 14:
- Install permanent traffic control and pour 12” pavement at Station 27
- Install daily traffic control at Stations 22, 23, 30, 31
- Install snowmelt platform ramps at Stations 27, 31
- Pour sidewalk at Stations 30, 31
- Form and pour ramps at Station 31
Week of November 21:
- Install permanent traffic control and pour platform ramps at Station 27
- Install daily traffic control at Station 31
- Pour sidewalk at Stations 27, 31
Week of November 28:
- Install permanent traffic control at Station 27
- Install daily traffic control at Station 31
- Pour sidewalk at Stations 27, 31
East-West Bus Rapid Transit Construction Updates will be updated weekly.