Week of October 31:
- Install permanent traffic control at Stations 22, 27
- Install daily traffic control at Stations 19, 23, 30, 31
- Pour 12” pavement at Stations 19, 31
- Pour sidewalk at Stations 25, 30
- Install snowmelt and pour platform at Station 27
- Install snowmelt ramps at Stations 30, 31
- Pour ramps at Station 30
- Form, pour, cure curb and gutter & form ramps at Station 31
Week of November 7:
- Install permanent traffic control at Stations 22, 27
- Install daily traffic control at Stations 23, 30, 31
- Restoration at Station 23
- Pour sidewalk at Stations 23, 30, 31
- Form and pour curb and gutter, form platform ramps & grade at Station 27
- Pour 12” pavement at Stations 27, 31
- Pour ramps at Stations 30, 31
- Install snowmelt ramps at Station 31
Week of November 14:
- Install permanent traffic control at Station 27
- Install daily traffic control at Stations 30, 31
- Install snowmelt platform ramps, pour platform ramps, and pour sidewalk at Station 27