Week of Nov. 1:
- Install permanent traffic control at Stations 1, 6, 11, 12, 14, 15, 17, 18, 19, 20
- Install daily traffic control at Station 10
- Install trench drain at Stations 4, 19
- Open roadway at Stations 6, 11, 12
- Median, Southside, and Northwest pavement concrete work at Station 6
- Backfill and restoration at Stations 10, 11, 12
- Form and pour curb and gutter at Stations 11, 12, 17
- Install sidewalk at Station 11
- Install 12” pavement at Stations 11, 12
- Install driveways at Station 12
- Install ramp and steps at Stations 12, 17
- Form platform and regrade Stations 14, 15, 17, 18
- Install snowmelt, pullboxes, and grounding ring and snowmelt inspection at Stations 14, 17, 19
- Pour platform at Stations 17, 19
- Survey Stations 17, 18
- Install conduit at Station 18
- Street light termination at Station 20
Week of Nov. 8:
- Install permanent traffic control at Stations 1, 14, 15, 17, 18, 19, 20
- Install daily traffic control, backfill and restoration at Station 12
- Snowmelt inspection and survey Stations 14, 15, 18, 19
- Pour platform at Stations 14, 15, 18
- Grading at Stations 14, 15
- Install ramp and steps at Stations 14, 15, 17, 18, 19
- Form and pour curb and gutter at Stations 14, 17, 19
- Install sidewalk at Stations 14, 15, 17, 19
- Install snowmelt, pull boxes, and grounding ring at Stations 15, 18, 19
- Install 12” pavement at Stations 15, 17, 19
- Install trenchdrain at Station 18
- Regrade Stations 18, 19
Week of Nov. 15:
- Install permanent traffic control at Stations 1, 14, 15, 17, 18, 19, 20
- Install sidewalk at Stations 14, 15, 18, 19
- Install 12” pavement at Stations 14, 15, 18, 19
- Open roadway at Stations 15, 17
- Install snowmelt, pull boxes, and grounding ring, snowmelt inspection, form and pour curb & gutter, and install ramp & steps at Station 18