Construction Update Three-Week Look Ahead November 5, 2021

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.

Week of Nov. 1:

  • Install permanent traffic control at Stations 1, 6, 11, 12, 14, 15, 17, 18, 19, 20
  • Install daily traffic control at Station 10
  • Install trench drain at Stations 4, 19
  • Open roadway at Stations 6, 11, 12
  • Median, Southside, and Northwest pavement concrete work at Station 6
  • Backfill and restoration at Stations 10, 11, 12
  • Form and pour curb and gutter at Stations 11, 12, 17
  • Install sidewalk at Station 11
  • Install 12” pavement at Stations 11, 12
  • Install driveways at Station 12
  • Install ramp and steps at Stations 12, 17
  • Form platform and regrade Stations 14, 15, 17, 18
  • Install snowmelt, pullboxes, and grounding ring and snowmelt inspection at Stations 14, 17, 19
  • Pour platform at Stations 17, 19
  • Survey Stations 17, 18
  • Install conduit at Station 18
  • Street light termination at Station 20

Week of Nov. 8:

  • Install permanent traffic control at Stations 1, 14, 15, 17, 18, 19, 20
  • Install daily traffic control, backfill and restoration at Station 12
  • Snowmelt inspection and survey Stations 14, 15, 18, 19
  • Pour platform at Stations 14, 15, 18
  • Grading at Stations 14, 15
  • Install ramp and steps at Stations 14, 15, 17, 18, 19
  • Form and pour curb and gutter at Stations 14, 17, 19
  • Install sidewalk at Stations 14, 15, 17, 19
  • Install snowmelt, pull boxes, and grounding ring at Stations 15, 18, 19
  • Install 12” pavement at Stations 15, 17, 19
  • Install trenchdrain at Station 18
  • Regrade Stations 18, 19

Week of Nov. 15:

  • Install permanent traffic control at Stations 1, 14, 15, 17, 18, 19, 20
  • Install sidewalk at Stations 14, 15, 18, 19
  • Install 12” pavement at Stations 14, 15, 18, 19
  • Open roadway at Stations 15, 17
  • Install snowmelt, pull boxes, and grounding ring, snowmelt inspection, form and pour curb & gutter, and install ramp & steps at Station 18

East-West Bus Rapid Transit Construction Updates will be updated weekly. 

construction-map-with-stations