Construction Update Three-Week Look Ahead October 28, 2021

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of Oct. 25:

  • Install permanent traffic control at Stations 1, 6, 9, 10, 11, 12, 14, 15, 17, 18, 19, 20
  • Install daily traffic control at Station 10
  • Install additional trench drain at Station 4
  • Median pavement concrete work and install City of Wauwatosa conduit at Station 6
  • Open roadway at Stations 9, 10
  • Install sidewalk at Stations 10, 11, 12
  • Form and pour curb and gutter at Stations 11, 12
  • Install driveways, ramp and steps, and 12” pavement at Station 12
  • Survey platform and install conduit at Stations 14, 15
  • Regrade Station 14
  • Form platform at Stations 14, 17, 19
  • Install snowmelt, pull boxes and grounding ring at Stations 14, 17, 19
  • Install base course at Station 15
  • Snowmelt inspection at Stations 17, 19
  • Street light termination at Stations 18, 20
  • Survey Stations 18, 20

Week of Nov. 1:

  • Install permanent traffic control at Stations 1, 6, 11, 12, 14, 15, 17, 18, 19, 20
  • Install daily traffic control at Stations 10, 11
  • Open roadway at Stations 6, 11
  • Backfill and restoration at Stations 10, 11
  • Install driveways and 12” pavement at Station 12
  • Install snowmelt, pull boxes and grounding ring at Stations 14, 15, 17, 18, 20
  • Grade and pour platform at Station 14
  • Survey Stations 14, 15, 17, 18, 19, 20
  • Install ramp and steps at Station 14
  • Regrade Stations 15, 17, 18, 19, 20
  • Form platform at Stations 15, 18, 20
  • Snowmelt inspection and pour platform at Stations 15, 17, 19
  • Install conduit at Stations 18, 20
  • Form and pour curb and gutter, install trenchdrain, and install ramp and steps at Station 19

Week of Nov. 8:

  • Install permanent traffic control at Stations 1, 12, 14, 15, 17, 18, 19, 20
  • Open roadway at Stations 12, 17
  • Install snowmelt, pull boxes and grounding ring at Stations 14, 18, 20
  • Snowmelt inspection at Stations 14, 15, 18, 20
  • Install ramp and steps at Stations 14, 15, 17, 18
  • Form and pour curb and gutter at Stations 14, 15, 18
  • Install sidewalk at Stations 14, 15, 17, 19
  • Install 12” pavement at Stations 14, 17, 19
  • Survey and pour platform at Stations 15, 18, 20
  • Grading at Stations 15, 20
  • Regrade and install trenchdrain at Stations 18
  • Manhole adjustment at Station 20

East-West Bus Rapid Transit Construction Updates will be updated weekly. 