Week of Oct. 25:
- Install permanent traffic control at Stations 1, 6, 9, 10, 11, 12, 14, 15, 17, 18, 19, 20
- Install daily traffic control at Station 10
- Install additional trench drain at Station 4
- Median pavement concrete work and install City of Wauwatosa conduit at Station 6
- Open roadway at Stations 9, 10
- Install sidewalk at Stations 10, 11, 12
- Form and pour curb and gutter at Stations 11, 12
- Install driveways, ramp and steps, and 12” pavement at Station 12
- Survey platform and install conduit at Stations 14, 15
- Regrade Station 14
- Form platform at Stations 14, 17, 19
- Install snowmelt, pull boxes and grounding ring at Stations 14, 17, 19
- Install base course at Station 15
- Snowmelt inspection at Stations 17, 19
- Street light termination at Stations 18, 20
- Survey Stations 18, 20
Week of Nov. 1:
- Install permanent traffic control at Stations 1, 6, 11, 12, 14, 15, 17, 18, 19, 20
- Install daily traffic control at Stations 10, 11
- Open roadway at Stations 6, 11
- Backfill and restoration at Stations 10, 11
- Install driveways and 12” pavement at Station 12
- Install snowmelt, pull boxes and grounding ring at Stations 14, 15, 17, 18, 20
- Grade and pour platform at Station 14
- Survey Stations 14, 15, 17, 18, 19, 20
- Install ramp and steps at Station 14
- Regrade Stations 15, 17, 18, 19, 20
- Form platform at Stations 15, 18, 20
- Snowmelt inspection and pour platform at Stations 15, 17, 19
- Install conduit at Stations 18, 20
- Form and pour curb and gutter, install trenchdrain, and install ramp and steps at Station 19
Week of Nov. 8:
- Install permanent traffic control at Stations 1, 12, 14, 15, 17, 18, 19, 20
- Open roadway at Stations 12, 17
- Install snowmelt, pull boxes and grounding ring at Stations 14, 18, 20
- Snowmelt inspection at Stations 14, 15, 18, 20
- Install ramp and steps at Stations 14, 15, 17, 18
- Form and pour curb and gutter at Stations 14, 15, 18
- Install sidewalk at Stations 14, 15, 17, 19
- Install 12” pavement at Stations 14, 17, 19
- Survey and pour platform at Stations 15, 18, 20
- Grading at Stations 15, 20
- Regrade and install trenchdrain at Stations 18
- Manhole adjustment at Station 20