East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below.
Week of October 3:
- Install permanent traffic control at Stations 1, 13, 22, 27
- Install daily traffic control at Stations 16, 19, 23, 25, 30, 31
- Form, pour, cure curb and gutter at Stations 13, 22
- Pour sidewalk at Station 16
- Remove concrete at Station 19
- Street light removals at Stations 27, 31
- Install snowmelt, pour platform, and install trench drain at Station 30
- Install platform conduit at Station 31
Week of October 10:
- Install permanent traffic control at Stations 1, 22, 27
- Install daily traffic control at Stations 19, 23, 30, 31
- Restoration at Stations 1, 16, 23
- Install platform conduit at Stations 19, 27
- Pour 12” pavement at Stations 19, 22
- Form, pour, cure curb and gutter at Stations 22, 30
- Install platform ramp snowmelt, form and pour ramps & pour sidewalk at Station 22
- Grade at Stations 27, 30
- Form platform at Stations 27, 31
- Survey staking at Station 30
Week of October 17:
- Install permanent traffic control at Stations 1, 22, 27
- Install daily traffic control at Stations 19, 30, 31
- Pour 12” pavement at Stations 19, 30
- Pour sidewalk at Station 22
- Install snowmelt at Stations 27, 31
- Grade, pour platform & form, pour, cure curb and gutter at Station 31
East-West Bus Rapid Transit Construction Updates will be updated weekly.