Construction Update Three-Week Look Ahead October 7, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of October 3:

  • Install permanent traffic control at Stations 1, 13, 22, 27
  • Install daily traffic control at Stations 16, 19, 23, 25, 30, 31
  • Form, pour, cure curb and gutter at Stations 13, 22
  • Pour sidewalk at Station 16
  • Remove concrete at Station 19
  • Street light removals at Stations 27, 31
  • Install snowmelt, pour platform, and install trench drain at Station 30
  • Install platform conduit at Station 31

Week of October 10:

  • Install permanent traffic control at Stations 1, 22, 27
  • Install daily traffic control at Stations 19, 23, 30, 31
  • Restoration at Stations 1, 16, 23
  • Install platform conduit at Stations 19, 27
  • Pour 12” pavement at Stations 19, 22
  • Form, pour, cure curb and gutter at Stations 22, 30
  • Install platform ramp snowmelt, form and pour ramps & pour sidewalk at Station 22
  • Grade at Stations 27, 30
  • Form platform at Stations 27, 31
  • Survey staking at Station 30

Week of October 17:

  • Install permanent traffic control at Stations 1, 22, 27
  • Install daily traffic control at Stations 19, 30, 31
  • Pour 12” pavement at Stations 19, 30
  • Pour sidewalk at Station 22
  • Install snowmelt at Stations 27, 31
  • Grade, pour platform & form, pour, cure curb and gutter at Station 31

East-West Bus Rapid Transit Construction Updates will be updated weekly.

Construction Map with Stations July 9, 2021