East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center.
Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below:
Week of Sept. 7:
- Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17
- Form/pour/cure curb and gutter at Station 3, 5
- Additional sawcutting and removal at Station 3
- Install sidewalk at Stations 3, 4, 5, 6
- Install snowmelt, pull boxes, and grounding ring at Stations 4, 5, 7, 8, 9
- Ramp re-work at Station 4
- Snowmelt inspection at Station 5, 9
- Install ramp and steps at Station 5
- Catch basin adjustments at Station 6
- Survey, pour platform, install trenchdrain at Station 7
- Grading at Stations 7, 8
- Survey platform at Stations 8, 12, 14
- Form platform at Stations 8, 11
- Manhole adjustment at Station 10
- Regrade Station 11
- Install conduit at Station 12
- Install sewer, curb, sidewalk and pavement at Station 14
- Common excavation and remove concrete pavement at Stations 15, 17
Week of Sept. 13:
- Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17
- Install daily traffic control at Stations 20, 21
- Install sidewalk at Station 3, 5, 6, 7
- Install 12” Pavement at Stations 3, 4, 5
- Install snowmelt, pull boxes and grounding ring at Stations 7, 8, 9, 11
- Snowmelt inspection at Stations 7, 8, 9, 11
- Install trenchdrain and drain pipe at Station 7
- Install ramp and steps and form and pour curb and gutter at Stations 7, 9
- Survey and pour platform at Stations 8, 9, 10, 11
- Grading at Stations 8, 9, 10
- Form platform at Stations 11, 12, 14
- Install conduit at Station 12, 14, 15, 17
- Regrade Station 12, 14
- Common excavation at Stations 15, 17, 18
- Install base course and survey platform at Stations 15, 17
- Remove concrete pavement at Station 17, 18
- Sawcutting at Stations 20, 21
Week of Sept. 20:
- Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17
- Install backfill and restoration at Station 3, 4, 5, 6
- Install 12” pavement at Stations 6, 7, 9
- Install sidewalk at Station 7
- Install snowmelt, pull boxes, and grounding ring and snowmelt inspection at Station 8, 10, 11, 12
- Install ramp and steps and form and pour curb and gutter at Station 8, 10, 11
- Install sidewalk at Station 8, 9, 10, 11
- Grading at Station 11
- Form platform at Stations 12, 17
- Pour platform at Station 12
- Survey platform at Station 12, 18
- Install conduit at Station 17, 18
- Conduit inspection and regrade Station 17
- Common excavation, install base course and remove concrete pavement at Station 18
East-West Bus Rapid Transit Construction Updates will be updated weekly.