Construction Update Three-Week Look Ahead September 10, 2021

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below:

Week of Sept. 7:

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17
  • Form/pour/cure curb and gutter at Station 3, 5
  • Additional sawcutting and removal at Station 3
  • Install sidewalk at Stations 3, 4, 5, 6
  • Install snowmelt, pull boxes, and grounding ring at Stations 4, 5, 7, 8, 9
  • Ramp re-work at Station 4
  • Snowmelt inspection at Station 5, 9
  • Install ramp and steps at Station 5
  • Catch basin adjustments at Station 6
  • Survey, pour platform, install trenchdrain at Station 7
  • Grading at Stations 7, 8
  • Survey platform at Stations 8, 12, 14
  • Form platform at Stations 8, 11
  • Manhole adjustment at Station 10
  • Regrade Station 11
  • Install conduit at Station 12
  • Install sewer, curb, sidewalk and pavement at Station 14
  • Common excavation and remove concrete pavement at Stations 15, 17

Week of Sept. 13:

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17
  • Install daily traffic control at Stations 20, 21
  • Install sidewalk at Station 3, 5, 6, 7
  • Install 12” Pavement at Stations 3, 4, 5
  • Install snowmelt, pull boxes and grounding ring at Stations 7, 8, 9, 11
  • Snowmelt inspection at Stations 7, 8, 9, 11
  • Install trenchdrain and drain pipe at Station 7
  • Install ramp and steps and form and pour curb and gutter at Stations 7, 9
  • Survey and pour platform at Stations 8, 9, 10, 11
  • Grading at Stations 8, 9, 10
  • Form platform at Stations 11, 12, 14
  • Install conduit at Station 12, 14, 15, 17
  • Regrade Station 12, 14
  • Common excavation at Stations 15, 17, 18
  • Install base course and survey platform at Stations 15, 17
  • Remove concrete pavement at Station 17, 18
  • Sawcutting at Stations 20, 21

Week of Sept. 20:

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17
  • Install backfill and restoration at Station 3, 4, 5, 6
  • Install 12” pavement at Stations 6, 7, 9
  • Install sidewalk at Station 7
  • Install snowmelt, pull boxes, and grounding ring and snowmelt inspection at Station 8, 10, 11, 12
  • Install ramp and steps and form and pour curb and gutter at Station 8, 10, 11
  • Install sidewalk at Station 8, 9, 10, 11
  • Grading at Station 11
  • Form platform at Stations 12, 17
  • Pour platform at Station 12
  • Survey platform at Station 12, 18
  • Install conduit at Station 17, 18
  • Conduit inspection and regrade Station 17
  • Common excavation, install base course and remove concrete pavement at Station 18

East-West Bus Rapid Transit Construction Updates will be updated weekly. 

construction-map-with-stations