Construction Update Three-Week Look Ahead September 23, 2022

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below. 

Week of September 19:

  • Install permanent traffic control at Stations 1, 13, 22, 27
  • Install daily traffic control at Stations 16, 23, 25, 26, 30, 31
  • Install overhead charger at Station 1
  • Install city street light connection at Station 13
  • Pour 12” pavement at Stations 16, 26
  • Form ramps at Station 16
  • Form platform and install snowmelt system at Station 22
  • Survey staking and grade at Stations 27, 30
  • Remove concrete, common excavation and subgrade & install base course at Station 27
  • Remove street lights at Stations 27, 31
  • Remove platform forms and adjust conduit at Station 30
  • Install platform conduit at Station 31

Week of September 26:

  • Install permanent traffic control at Stations 1, 13, 22, 27
  • Install daily traffic control at Stations 16, 23, 24, 25, 26, 30, 31
  • City street light connection at Station 13
  • Form, pour, cure curb and gutter at Stations 13, 22
  • Install platform ramp snowmelt, pour ramps, and pour sidewalk at Station 16
  • Grade at Stations 22, 27, 30, 31
  • Pour platform at Station 22
  • Set shelter at Stations 23, 24, 25, 26
  • Remove street lights at Station 27
  • Install platform conduit at Stations 27, 31
  • Survey staking, form platform, and install snowmelt at Stations 30, 31
  • Adjust conduit at Station 30

Week of October 3:

  • Install permanent traffic control at Stations 1, 13, 22, 27
  • Install daily traffic control at Stations 16, 30, 31
  • Install 12” pavement, form ramps, install platform ramp snowmelt, and pour sidewalk at Station 22
  • Form platform at Stations 27, 30
  • Install snowmelt at Stations 27, 30, 31
  • Install trench drain at Station 30
  • Form, pour, cure curb and gutter & grade at Station 31

East-West Bus Rapid Transit Construction Updates will be updated weekly.

construction map with stations