Construction Update Three-Week Look Ahead September 24, 2021

Construction Update

East-West Bus Rapid Transit (BRT) is Milwaukee County’s planned 9-mile regional, modern transit service connecting downtown Milwaukee, Milwaukee’s Near West Side, Marquette University, Wauwatosa and the Milwaukee Regional Medical Center. 

Although on-site crews may occasionally communicate specific impacts to your property, a general outline of what to expect in the coming weeks is listed below:

Week of September 20:

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17, 18, 19
  • Install 12” pavement at Stations 3, 4, 5, 6
  • Install sidewalk at Stations 5, 6, 7
  • Install snowmelt, pull boxes and grounding ring and snowmelt inspection at Stations 7, 8, 9
  • Survey Stations 7, 9, 10
  • Form and pour curb and gutter and install ramp and steps at Stations 7, 9
  • Pour platform at Station 8
  • Grading at Stations 8, 10, 11
  • Connect trenchdrain at Station 10
  • Tree removal at Station 11
  • Install conduit at Stations 12, 14, 17
  • Regrade and form platform at Station 14
  • Conduit inspection at Station 17
  • Survey platform at Stations 18, 19
  • Common excavation, install base course and street light relocate at Station 19

Week of September 27:

  • Install permanent traffic control at Stations 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17, 18, 19
  • Backfill and restoration and open roadway at Stations 3, 4, 5
  • Install 12” pavement at Station 6, 7, 8, 9, 10
  • Snowmelt inspection at Station 7, 8, 10, 11, 12, 14, 17
  • Install sidewalk, ramp and steps at Station 7, 8, 9, 10
  • Install snowmelt, pull boxes and grounding ring at Station 8, 10, 11, 12, 14, 17
  • Survey Station 8
  • Form and pour curb and gutter at Station 8, 9, 10
  • Form platform at Station 11, 12, 17, 19
  • Pour platform at Station 11, 14
  • Grading at Station 11
  • Install conduit and regrade Station 12, 17, 19
  • Common excavation, survey, install base course and remove concrete pavement at Station 15
  • Conduit inspection at Station 17
  • Street light relocate at Station 18

Week of October 4:

  • Install permanent traffic control at Stations 1, 6, 7, 8, 9, 10, 11, 12, 14, 15, 17, 18, 19, 20
  • Open roadway at Stations 6, 7, 8, 9
  • Install 12” pavement at Stations 10, 11
  • Survey Stations 11, 12, 17, 19
  • Form and pour curb and gutter and install ramp and steps at Stations 11, 12, 17
  • Install sidewalk at Station 11
  • Pour platform at Stations 12, 17, 19
  • Grading at Station 12
  • Install conduit at Stations 15, 18, 20
  • Regrade Stations 15, 17, 18, 19
  • Form platform at Stations 15, 18
  • Install snowmelt, pull boxes and grounding ring and snowmelt inspection at Station 19
  • Install base course, survey platform, common excavation, remove concrete pavement at Station 20

East-West Bus Rapid Transit Construction Updates will be updated weekly. 